PROJECT TITLE:
MVH Sliding Track Modernization
Contracts:
MVH.24.006.150, EXO.24.005.101, MVH.24.006.150, MVH.24.006.140, MVH.24.006.130, MVH.24.006.160, MVH.24.006.203, MVH.24.006.120, MVH.24.006.110
PROJECT IDENTIFICATION NUMBER:
MVH.24.006
LOCATION:
31 Van Hoevenberg Way
Lake Placid, NY 12946
Lake Placid, NY 12946
PROJECT CONTRACTS:
CONTRACT NUMBER: | CONTRACT DESCRIPTION: | MWBE GOAL M - W: | SDVOB GOAL: | ESTIMATED COST: | PLANS & SPECS AVAILABLE BY: | BIDS TO BE RECEIVED BY: |
CONTRACT NUMBER: MVH.24.006.170 | CONTRACT DESCRIPTION: Track Lighting System Installation | MWBE GOAL M - W: 0% - 0% | SDVOB GOAL: 0% | ESTIMATED COST: $3,500,000-$4,500,000 | PLANS & SPECS AVAILABLE BY: 4/2/2025 | BIDS TO BE RECEIVED BY: 5/6/2025 (12:00 PM) BID STATUS: Complete (VIEW BID RESULTS) |
CONTRACT NUMBER: EXO.24.005.101 | CONTRACT DESCRIPTION: Hourly Term Contract for Ammonia Piping | MWBE GOAL M - W: 0% - 0% | SDVOB GOAL: 0% | ESTIMATED COST: $2,500,000–3,000,000 | PLANS & SPECS AVAILABLE BY: 4/1/2025 | BIDS TO BE RECEIVED BY: 4/29/2025 (2:00 PM) BID STATUS: Complete – Not Awarded (NO BIDS RECEIVED) |
CONTRACT NUMBER: MVH.24.006.150 | CONTRACT DESCRIPTION: Timing & Ops and Start 3 Superstructures Contract | MWBE GOAL M - W: 3% - 7.6% | SDVOB GOAL: 3% | ESTIMATED COST: $5,000,000-$6,500,000 | PLANS & SPECS AVAILABLE BY: 3/18/2025 | BID STATUS: Withdrawn |
CONTRACT NUMBER: MVH.24.006.140 | CONTRACT DESCRIPTION: Track Curve and Roof Structure Improvements | MWBE GOAL M - W: 0%-1% | SDVOB GOAL: 10.6% | ESTIMATED COST: $10,000,000-$12,000,000 | PLANS & SPECS AVAILABLE BY: 2/13/2025 | BIDS TO BE RECEIVED BY: 3/14/2025 (11:00 AM) BID STATUS: Complete (VIEW BID RESULTS) |
CONTRACT NUMBER: MVH.24.006.130 | CONTRACT DESCRIPTION: Site Utilities and Finishes Contract | MWBE GOAL M - W: 1%-1.6% | SDVOB GOAL: 3% | ESTIMATED COST: $12,000,000-$14,000,000 | PLANS & SPECS AVAILABLE BY: 2/13/2025 | BIDS TO BE RECEIVED BY: 3/7/2025 BID STATUS: Complete (VIEW BID RESULTS) |
CONTRACT NUMBER: MVH.24.006.160 | CONTRACT DESCRIPTION: Start 1 and Start 3 Buildings Contract | MWBE GOAL M - W: 0% | SDVOB GOAL: 0% | ESTIMATED COST: $6,000,000-$8,000,000 | PLANS & SPECS AVAILABLE BY: 1/23/2025 | BIDS TO BE RECEIVED BY: 3/10/2025 BID STATUS: Complete – Not Awarded (VIEW BID RESULTS) |
CONTRACT NUMBER: MVH.24.006.203 | CONTRACT DESCRIPTION: Structural Steel and Glulam Procurement | MWBE GOAL M - W: 0% | SDVOB GOAL: 0% | ESTIMATED COST: $3,000,000-$4,000,000 | PLANS & SPECS AVAILABLE BY: 12/24/2024 | BIDS TO BE RECEIVED BY: 1/21/2025 BID STATUS: Complete (VIEW BID RESULTS) |
CONTRACT NUMBER: MVH.24.006.120 | CONTRACT DESCRIPTION: Site Logistic, Early Works, and Pile Installation | MWBE GOAL M - W: 1%-17.9% | SDVOB GOAL: 3% | ESTIMATED COST: $8,000,000-$10,000,000 | PLANS & SPECS AVAILABLE BY: 12/13/2024 | BIDS TO BE RECEIVED BY: 1/15/2025 BID STATUS: Complete (VIEW BID RESULTS) |
CONTRACT NUMBER: MVH.24.006.110 | CONTRACT DESCRIPTION: Refrigeration Plant Replacement | MWBE GOAL M - W: 1%-6.3% | SDVOB GOAL: 3% | ESTIMATED COST: $13,500,000-$15,500,000 | PLANS & SPECS AVAILABLE BY: 11/22/2024 | BIDS TO BE RECEIVED BY: 12/19/2024 BID STATUS: Complete (VIEW BID RESULTS) |
REGISTERED BIDDER LISTS:
The companies listed below have registered to bid on Contract Number: CONTRACT NUMBER: MVH.24.006.170 |
||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: |
COMPANY NAME: Con Tech Building Systems, Inc. | COMPANY ADDRESS: 4524 State Highway 58 Suite 1 Gouverneur, NY 13642 | PHONE NUMBER: (315) 569-8672 |
COMPANY NAME: S&L Electric, Inc. | COMPANY ADDRESS: 5313 State Highway 56 Colton, NY 13625 | PHONE NUMBER: (315) 262-2631 |
COMPANY NAME: Gross Electric, Inc. | COMPANY ADDRESS: 27 Silver Circle Queensbury, NY 12804 | PHONE NUMBER: (518) 792-0216 |
COMPANY NAME: Swan Contracting | COMPANY ADDRESS: 50A Reading Road Watervliet, NY12198 | PHONE NUMBER: (518) 675-0904 |
The companies listed below have registered to bid on Contract Number: CONTRACT NUMBER: EXO.24.005.101 |
||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: |
COMPANY NAME: Mullally Bros. Inc. | COMPANY ADDRESS: 116 Campbell Ave. Troy, NY 12180 | PHONE NUMBER: (518) 272-7061 |
COMPANY NAME: Mollenberg-Betz | COMPANY ADDRESS: 300 Scott Street Buffalo, NY 14204 | PHONE NUMBER: (716) 614-7473 |
The companies listed below have registered to bid on Contract Number: CONTRACT NUMBER: MVH.24.006.150 |
||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: |
COMPANY NAME: MLB Construction Services, LLC | COMPANY ADDRESS: 1 Stonebreak Road Malta, NY 12020 | PHONE NUMBER: (518) 289-1371 |
COMPANY NAME: Kubricky-Jointa Lime, LLC | COMPANY ADDRESS: 269 Ballard Road Wilton, NY 12831 | PHONE NUMBER: (518) 792-5864 |
COMPANY NAME: Con Tech Building Systems, Inc. | COMPANY ADDRESS: 4524 State Highway 58 Suite 1 Gouverneur, NY 13642 | PHONE NUMBER: (315) 287-0135 |
The companies listed below have registered to bid on Contract Number: CONTRACT NUMBER: MVH.24.006.140 |
||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: |
COMPANY NAME: Kubricky-Jointa Lime, LLC | COMPANY ADDRESS: 269 Ballard Road Wilton, NY 12831 | PHONE NUMBER: (518) 792-5864 |
COMPANY NAME: Nuvista Design General Contractors LLC. | COMPANY ADDRESS: 589 Greenbush Road Blauvelt NY 10913 | PHONE NUMBER: (914) 393-6581 |
COMPANY NAME: Rifenburg Contracting Corp. | COMPANY ADDRESS: 121 Defreest Drive Troy, NY 12180 | PHONE NUMBER: (518) 279-3967 |
The companies listed below have registered to bid on Contract Number: MVH.24.006.130 |
||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: |
COMPANY NAME: Jersen Construction Group, LLC | COMPANY ADDRESS: 6 Industry Drive Waterford, New York 12188 | PHONE NUMBER: (518) 233-0600 |
COMPANY NAME: Reale Construction | COMPANY ADDRESS: 411 County Route 56 Ticonderoga, NY 12883 | PHONE NUMBER: (518) 586-0471 |
COMPANY NAME: Upstate Companies | COMPANY ADDRESS: 1690 State Highway 8 Mount Upton, NY 13809 | PHONE NUMBER: (607) 386-2402 |
COMPANY NAME: Rifenburg Contracting Corporation | COMPANY ADDRESS: 121 Defreest Drive Troy, New York 12180 | PHONE NUMBER: (518) 365-9969 |
COMPANY NAME: Kubricky-Jointa Lime, LLC | COMPANY ADDRESS: 269 Ballard Road Wilton, NY 12831 | PHONE NUMBER: (518) 792-5864 |
The companies listed below have registered to bid on Contract Number: MVH.24.006.160 |
||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: |
COMPANY NAME: Jersen Construction Group, LLC | COMPANY ADDRESS: 6 Industry Drive Waterford, NY 12188 | PHONE NUMBER: (518) 233-0600 |
COMPANY NAME: Rifenburg Contracting Corp. | COMPANY ADDRESS: 121 Defreest Drive Troy, NY 12180 | PHONE NUMBER: (518) 279-3967 |
COMPANY NAME: L.H. LAPLANTE | COMPANY ADDRESS: 52 Main Mill St Plattsburgh, NY 12901 | PHONE NUMBER: (518) 561-8003 |
COMPANY NAME: Cutting Edge Group, LLC | COMPANY ADDRESS: 1810 STATE ROUTE 9 Suite B Lake George, NY 12845 | PHONE NUMBER: (518) 321-1499 |
COMPANY NAME: MJ Raymond Construction | COMPANY ADDRESS: 1026 NYS RT 3 Saranac Lake, NY 12983 | PHONE NUMBER: (518) 891-8822 |
COMPANY NAME: Rozell Industries | COMPANY ADDRESS: 129 Park Road Rozell Industires Queensbury, NY 12804 | PHONE NUMBER: (518) 793-2634 |
COMPANY NAME: PC Construction Company dba PCEO | COMPANY ADDRESS: 193 TIlley Drive South Burlington, VT 05403 | PHONE NUMBER: (802) 658-4100 |
COMPANY NAME: Kingsbury Companies | COMPANY ADDRESS: 58 Center Road Middlesex, VT 05602 | PHONE NUMBER: (802) 496-2205 |
COMPANY NAME: MLB Construction Services, LLC | COMPANY ADDRESS: 1 Stonebreak Road Malta, NY 12020 | PHONE NUMBER: (518) 289-1371 |
The companies listed below have registered to bid on Contract Number: MVH.24.006.203 |
||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: |
COMPANY NAME: Kubricky-Jointa Lime, LLC | COMPANY ADDRESS: 269 Ballard Road Wilton, NY 12831 | PHONE NUMBER: (518) 792-5864 |
COMPANY NAME: Unalam | COMPANY ADDRESS: 18 Clifton Street P.O. Box K Unadilla, NY 13849 | PHONE NUMBER: (607) 369-9341 |
COMPANY NAME: New Energy Works | COMPANY ADDRESS: 1180 Commercial Drive Farmington, NY 14425 | PHONE NUMBER: (585) 626-2472 |
COMPANY NAME: Goodfellow | COMPANY ADDRESS: 225 Rue Goodfellow Delson, Québec J5B 1V Canada | PHONE NUMBER: (514) 809-0532 |
COMPANY NAME: Rifenburg Contracting Corp. | COMPANY ADDRESS: 121 Defreest Drive Troy, NY 12180 | PHONE NUMBER: (518) 279-3967 |
The companies listed below have registered to bid on Contract Number: MVH.24.006.120 |
||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: |
COMPANY NAME: PCEO | COMPANY ADDRESS: 193 TIlley Drive South Burlington, VT 05403 | PHONE NUMBER: (802) 658-4100 |
COMPANY NAME: Kubricky-Jointa Lime, LLC | COMPANY ADDRESS: 269 Ballard Road Wilton, NY 12831 | PHONE NUMBER: (518) 792-5864 |
COMPANY NAME: CD Perry, LLC | COMPANY ADDRESS: 9 Monroe Street PO Box 866 Troy, NY 12180 | PHONE NUMBER: (518) 728-8309 |
COMPANY NAME: Rifenburg Contracting Corporation | COMPANY ADDRESS: 121 Defreest Drive Troy, NY 12180 | PHONE NUMBER: (518) 279-3967 |
COMPANY NAME: Jersen Construction Group, LLC | COMPANY ADDRESS: 6 Industry Drive Waterford, NY 12188 | PHONE NUMBER: (518) 233-0600 |
COMPANY NAME: James H. Maloy, Inc | COMPANY ADDRESS: 421 Albany Shaker Road PO Box 11016 Loudonville, NY 12211 | PHONE NUMBER: (518) 438-7881 |
COMPANY NAME: Luck Bros., Inc. | COMPANY ADDRESS: 73 Trade Road Plattsburgh, NY 12901 | PHONE NUMBER: (518) 561-4321 |
COMPANY NAME: Kingsbury Companies | COMPANY ADDRESS: 58 Center Road Middlesex, VT 05602 | PHONE NUMBER: (802) 224-6176 |
COMPANY NAME: REALE CONSTRUCTION | COMPANY ADDRESS: 411 County Rt 56 Ticonderoga, NY 12883 | PHONE NUMBER: (518) 586-0471 |
COMPANY NAME: Richard Goettle, Inc. (Goettle) | COMPANY ADDRESS: 12071 Hamilton Ave. Cincinnati, OH 45231 | PHONE NUMBER: (412) 298-9139 |
The companies listed below have registered to bid on Contract Number: MVH.24.006.110 |
||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: |
COMPANY NAME: MLB Construction Services, LLC | COMPANY ADDRESS: 1 Stonebreak Road Malta, NY 12020 | PHONE NUMBER: (518) 289-1374 |
COMPANY NAME: Jersen Construction Group, LLC | COMPANY ADDRESS: 6 Industry Drive Waterford, NY 12188 | PHONE NUMBER: (518) 233-0600 |
COMPANY NAME: PC Construction Company dba PCEO | COMPANY ADDRESS: 193 Tilley Drive South Burlington, VT 05403 | PHONE NUMBER: (802) 658-4100 |
COMPANY NAME: Kubricky-Jointa Lime, LLC | COMPANY ADDRESS: 269 Ballard Road Wilton, NY 12831 | PHONE NUMBER: (518) 792-5864 |
COMPANY NAME: L.H. LAPLANTE | COMPANY ADDRESS: 52 Main Mill St Plattsburgh, NY 12901 | PHONE NUMBER: (518) 561-8003 |
COMPANY NAME: FPI Mechanical Inc. | COMPANY ADDRESS: 11 Green Mountain Dr. Cohoes, NY 12047 | PHONE NUMBER: (518) 783-7066 |
INTERESTED SUBCONTRACTOR & SUPPLIER LISTS:
The companies listed below have registered as interested subcontractors and/or suppliers for Contract Number: MVH.24.006.150 (PLEASE NOTE: The New York State Olympic Regional Development Authority does not guarantee the accuracy of any third-party information below and takes no responsibility for any transactions undertaken or contractual relationships entered into between third parties as a result of the information provided.) |
|||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: | INTERESTED SPEC CODE/TITLE: |
COMPANY NAME: Pipeline Mechanical of Plattsburgh, LLC | COMPANY ADDRESS: 102 Trade Road Plattsburgh, NY 12901 | PHONE NUMBER: (518) 324-2419 | INTERESTED SPEC CODE/TITLE: Plumbing & HVAC |
COMPANY NAME: All Safe Sprinkler Company, LLC | COMPANY ADDRESS: 4424 Rotue 22 Plattsburgh, NY 12901 | PHONE NUMBER: (518) 563-4400 | INTERESTED SPEC CODE/TITLE: Fire Protection |
COMPANY NAME: S&L Electric, Inc | COMPANY ADDRESS: 5313 State Highway 56 Colton, NY 13625 | PHONE NUMBER: (315) 262-2631 | INTERESTED SPEC CODE/TITLE: Electrical |
The companies listed below have registered as interested subcontractors and/or suppliers for Contract Number: MVH.24.006.140 (PLEASE NOTE: The New York State Olympic Regional Development Authority does not guarantee the accuracy of any third-party information below and takes no responsibility for any transactions undertaken or contractual relationships entered into between third parties as a result of the information provided.) |
|||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: | INTERESTED SPEC CODE/TITLE: |
COMPANY NAME: WB Safety & Engineering | COMPANY ADDRESS: 1971 Western Ave #269 Albany, NY 12203 | PHONE NUMBER: (518) 788-8617 | INTERESTED SPEC CODE/TITLE: Fall Protection & Roof Access System Design, Supply, Installation, Inspection & Training, Safety Consulting & Engineering. |
The companies listed below have registered as interested subcontractors and/or suppliers for Contract Number: MVH.24.006.130 (PLEASE NOTE: The New York State Olympic Regional Development Authority does not guarantee the accuracy of any third-party information below and takes no responsibility for any transactions undertaken or contractual relationships entered into between third parties as a result of the information provided.) |
|||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: | INTERESTED SPEC CODE/TITLE: |
COMPANY NAME: Upstate Companies | COMPANY ADDRESS: 1690 State Highway 8 Mount Upton, New York 13809 | PHONE NUMBER: (607) 386-2402 | INTERESTED SPEC CODE/TITLE: General Construction |
COMPANY NAME: Reale Construction | COMPANY ADDRESS: 411 County Route 56 Ticonderoga, NY 12883 | PHONE NUMBER: (518) 586-0471 | INTERESTED SPEC CODE/TITLE: Civil |
The companies listed below have registered as interested subcontractors and/or suppliers for Contract Number: MVH.24.006.160 (PLEASE NOTE: The New York State Olympic Regional Development Authority does not guarantee the accuracy of any third-party information below and takes no responsibility for any transactions undertaken or contractual relationships entered into between third parties as a result of the information provided.) |
|||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: | INTERESTED SPEC CODE/TITLE: |
COMPANY NAME: L.H. LAPLANTE | COMPANY ADDRESS: 52 Main Mill St Plattsburgh, NY 12901 | PHONE NUMBER: (518) 561-8003 | INTERESTED SPEC CODE/TITLE: HVAC/ Plumbing Subcontractor |
COMPANY NAME: MJ Raymond Construction | COMPANY ADDRESS: 1026 NYS RT 3 Saranac Lake, NY 12983 | PHONE NUMBER: (518) 891-8822 | INTERESTED SPEC CODE/TITLE: NYS Certified WBE - Civil Contractor |
COMPANY NAME: Reale Construction | COMPANY ADDRESS: PO Box 56 2928 Plank Road Moriah Center, NY 1296 | PHONE NUMBER: (518) 586-0471 | INTERESTED SPEC CODE/TITLE: Sitework |
COMPANY NAME: FRsix | COMPANY ADDRESS: 4-74 48th Avenue, Unit 24J Long Island City, NY 11109 | PHONE NUMBER: (617) 694-6321 | INTERESTED SPEC CODE/TITLE: SDVOB |
COMPANY NAME: BR Johnson | COMPANY ADDRESS: 6960 Fly Road East Syracuse, NY 13057 | PHONE NUMBER: (315) 565-3340 | INTERESTED SPEC CODE/TITLE: Subcontractor |
COMPANY NAME: Northline Utilities, LLC | COMPANY ADDRESS: 15 School Lane Au Sable Forks, NY 12912 | PHONE NUMBER: (518) 647-8198 | INTERESTED SPEC CODE/TITLE: Electrical |
COMPANY NAME: S&L Electric, Inc. | COMPANY ADDRESS: 5313 State Highway 56 Colton, NY 13625 | PHONE NUMBER: (315) 262-2631 | INTERESTED SPEC CODE/TITLE: Electrical, Communications |
COMPANY NAME: PHLY Surety | COMPANY ADDRESS: 1 Lakeshore Center Suite 300 Bridgewater, MA 02324 | PHONE NUMBER: (781) 297-6568 | INTERESTED SPEC CODE/TITLE: Surety |
The companies listed below have registered as interested subcontractors and/or suppliers for Contract Number: MVH.24.006.203 (PLEASE NOTE: The New York State Olympic Regional Development Authority does not guarantee the accuracy of any third-party information below and takes no responsibility for any transactions undertaken or contractual relationships entered into between third parties as a result of the information provided.) |
|||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: | INTERESTED SPEC CODE/TITLE: |
COMPANY NAME: Tridome Structures | COMPANY ADDRESS: 50 Howe Ave. Bldg. R Millbury, MA 01527 | PHONE NUMBER: (720) 595-1989 | INTERESTED SPEC CODE/TITLE: Glulam Manufacturer |
COMPANY NAME: Unalam | COMPANY ADDRESS: 18 Clifton Street P.O. Box K Unadilla, NY 13849 | PHONE NUMBER: (607) 369-9341 | INTERESTED SPEC CODE/TITLE: Glulam Manufacturer |
COMPANY NAME: R & S Steel, LLC | COMPANY ADDRESS: 412 Canal Street Rome, NY 13440 | PHONE NUMBER: (315) 281-0123 | INTERESTED SPEC CODE/TITLE: Structural Steel Fabricator and Erector |
COMPANY NAME: South County Post and Beam | COMPANY ADDRESS: 521 Liberty Ln West Kingston, RI 02892 | PHONE NUMBER: (401) 783-4415 | INTERESTED SPEC CODE/TITLE: Glulam Fabricator & Installer |
The companies listed below have registered as interested subcontractors and/or suppliers for Contract Number: MVH.24.006.120 (PLEASE NOTE: The New York State Olympic Regional Development Authority does not guarantee the accuracy of any third-party information below and takes no responsibility for any transactions undertaken or contractual relationships entered into between third parties as a result of the information provided.) |
|||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: | INTERESTED SPEC CODE/TITLE: |
COMPANY NAME: dba Engineered Pile Solutions, Veteran Materials Co., LLC | COMPANY ADDRESS: 38 Garden Parkway Buffalo, NY 14221 | PHONE NUMBER: (716) 353-6370 | INTERESTED SPEC CODE/TITLE: Steel Pile Supplier & Accessories |
COMPANY NAME: CD Perry, LLC | COMPANY ADDRESS: 9 Monroe Street O Box 866 Troy, NY 12180 | PHONE NUMBER: 518) 728-8309 | INTERESTED SPEC CODE/TITLE: Civil & Foundations |
COMPANY NAME: Maine Drilling & Blasting | COMPANY ADDRESS: 88 Gold Ledge Ave Auburn, NH 03032 | PHONE NUMBER: (207) 240-0999 | INTERESTED SPEC CODE/TITLE: Micropile |
COMPANY NAME: Cristo Demolition, Inc. | COMPANY ADDRESS: 241 North Pearl State Albany, NY 12207 | PHONE NUMBER: (518) 463-6985 | INTERESTED SPEC CODE/TITLE: Abatement & Demolition |
COMPANY NAME: Upstone Materials | COMPANY ADDRESS: 909 State Rte 3, Sarnac Lake, NY 12983 | PHONE NUMBER: (518) 891-0236 | INTERESTED SPEC CODE/TITLE: Concrete, Asphalt, Aggregate, Paving |
COMPANY NAME: Luck Bros., Inc. | COMPANY ADDRESS: 73 Trade Road Plattsburgh, NY 12901 | PHONE NUMBER: (518) 561-4321 | INTERESTED SPEC CODE/TITLE: Civil - Sitework |
COMPANY NAME: Keller North America Inc. | COMPANY ADDRESS: 1140 Crosspointe Ln Suite 4 Webster, NY 14580 | PHONE NUMBER: (315) 882-1980 | INTERESTED SPEC CODE/TITLE: Micropile Installer, Design Build |
COMPANY NAME: ARRAY Construction Services | COMPANY ADDRESS: 1551 E Genesee Street Skaneateles, NY 13152 | PHONE NUMBER: (315) 521-0815 | INTERESTED SPEC CODE/TITLE: Micropile |
COMPANY NAME: SperryCo, LLC | COMPANY ADDRESS: 3624 Dixon Rd Mannsville, NY 13661 | PHONE NUMBER: (315) 816-1881 | INTERESTED SPEC CODE/TITLE: NYS WBE - Micropiles |
The companies listed below have registered as interested subcontractors and/or suppliers for Contract Number: MVH.24.006.110 (PLEASE NOTE: The New York State Olympic Regional Development Authority does not guarantee the accuracy of any third-party information below and takes no responsibility for any transactions undertaken or contractual relationships entered into between third parties as a result of the information provided.) |
|||
COMPANY NAME: | COMPANY ADDRESS: | PHONE NUMBER: | INTERESTED SPEC CODE/TITLE: |
COMPANY NAME: Upstone Materials | COMPANY ADDRESS: 909 State Rte 3, Sarnac Lake, NY 12983 | PHONE NUMBER: (518) 891-0236 | INTERESTED SPEC CODE/TITLE: Concrete, Asphalt, Aggregate, Paving |
COMPANY NAME: Northline Utilities, LLC | COMPANY ADDRESS: 15 School Lane Au Sable Forks, NY 12912 | PHONE NUMBER: (518) 647-8198 | INTERESTED SPEC CODE/TITLE: Electrical |
COMPANY NAME: Pipeline Mechanical of Plattsburgh, LLC | COMPANY ADDRESS: 102 Trade Road Plattsburgh, NY 12901 | PHONE NUMBER: (518) 324-2419 | INTERESTED SPEC CODE/TITLE: Plumbing & HVAC |
COMPANY NAME: Grasshopper Gardens | COMPANY ADDRESS: 318 Mott Road Gansevoort, NY 12831 | PHONE NUMBER: (518) 760-6062 | INTERESTED SPEC CODE/TITLE: Landscaping |
COMPANY NAME: Rifenburg Contracting Corporation | COMPANY ADDRESS: 121 Defreest Drive Troy, NY 12180 | PHONE NUMBER: (518) 365-9969 | INTERESTED SPEC CODE/TITLE: Sitework, Excavation, Excavation and installation of underground utilities. |
COMPANY NAME: Mullally Bros. Inc | COMPANY ADDRESS: 116 Campbell Ave. Troy, NY 12180 | PHONE NUMBER: (518) 272-7061 | INTERESTED SPEC CODE/TITLE:: Industrial Refrigeration Installation, Service |
COMPANY NAME: Mollenberg-Betz Inc. | COMPANY ADDRESS: 300 Scott Street Buffalo, NY 14204 | PHONE NUMBER: (716) 614-7473 | INTERESTED SPEC CODE/TITLE: Refrigeration |
COMPANY NAME: Mavec Advisors LLC | COMPANY ADDRESS: 11 Hidden Pond Path Suite 1A Wading River, NY 11792 | PHONE NUMBER: (631) 747-0372 | INTERESTED SPEC CODE/TITLE: Millwork & Refrigeration |
COMPANY NAME: S&L Electric, Inc. | COMPANY ADDRESS: 5313 State Highway 56 Colton, NY 13625 | PHONE NUMBER: (315) 262-2631 | INTERESTED SPEC CODE/TITLE: Subcontractor |
COMPANY NAME: Gross Electric, Inc. | COMPANY ADDRESS: 27 Silver Circle Queensbury, NY 12804 | PHONE NUMBER: (518) 792-0216 | INTERESTED SPEC CODE/TITLE: Electrical |
COMPANY NAME: Next Era Contracting, Inc. | COMPANY ADDRESS: 497 Water Street North Lawrence, NY 12967 | PHONE NUMBER: (518) 521-7424 | INTERESTED SPEC CODE/TITLE: Electrical |
COMPANY NAME: L.H. LAPLANTE | COMPANY ADDRESS: 52 Main Mill St. Plattsburgh, NY 12901 | PHONE NUMBER: (518) 561-8003 | INTERESTED SPEC CODE/TITLE: HVAC Subcontractor |
COMPANY NAME: MJ Raymond Construction LLC (NYS Certified WBE) | COMPANY ADDRESS: 1026 NYS RT. 3 Saranac Lake, NY 12983 | PHONE NUMBER: (518) 891-8822 | INTERESTED SPEC CODE/TITLE: Civil Contractor |
COMPANY NAME: BPI Mechanical Service | COMPANY ADDRESS: 5 Hemlock St. PO Box 336 Latham, NY 12110 | PHONE NUMBER: (518) 326-8450 | INTERESTED SPEC CODE/TITLE: Refrigeration |
RFI - QUESTION & ANSWER LISTS:
Below is a list of RFI questions submitted, along with accompanying answers for Contract Number: MVH.24.006.170 |
|||
RFI #: | QUESTION: | ADDENDUM #: | ANSWER: |
RFI #: 1 | QUESTION: Overhangs on Turns with recessed lights in them. Are the overhangs to be removed/demoed and new lights adhered to bumper overhang. Or is the overhang area with the recessed lights getting resurfaced to cover holes left behind by old lighting? What condition are the overhangs in to support weight of new fixtures? | ADDENDUM #: | ANSWER: Overhangs with lights are being demo'd in all areas except for curves 6 and 7, where there is no existing or new roof structure. These curves will have the lights removed and fixtures installed and remaining open space infilled as shown in detail 1/E501A, Curbe 6 and Curve 7 mounting detail. OVerhands are 2x4 construction and are expected to be in accceptabe condition to support the new lights. |
RFI #: 2 | QUESTION: New conduit to be ran for Emergency lighting circuits? | ADDENDUM #: | ANSWER: Yes. |
RFI #: 3 | QUESTION: How is the RS 485 cable supposed to be ran from Control rack to each DMX box? | ADDENDUM #: | ANSWER: Outdoor rated CAT 5E cable is run from the control rack to the DMX boxes. Cable should be run in a conduit underground from turn 10 to the track, approximately 10ft away, then into existing cable tray mounted the entire length of the track. Therea are 7 runs of CAT 5E cable total, daisy chaining the DMX boxes together, as shown on the tables provided on E003. Each DMX box will be mounted near the existing cable tray. |
RFI #: 4 | QUESTION: In reference to General Noes section on ED101, is "track lighting" referring to the location of light fixtures over the track or a type of light fixture known as 'track lighting'? | ADDENDUM #: | ANSWER: On ED101, "track lighting" refers to all existing track lighting to be demo'd. The pictures provided show the general types and layout of lighting to be removed for each section of track. EC to walk job site to determine total amount of effort required for the demo scope. |
RFI #: 5 | QUESTION: Is the electrical demo and new wire work on the building at Turn 10 continuing despite the building not being torn down and rebuilt anymore? | ADDENDUM #: | ANSWER: The building at turn 10 was never being torn down. This is an existing shed which will remain. The generator must be relocated (see addendum 2) and the transformer replaced, electrical upgraded per E700. You are referencing the Timing / Ops building which will be built the following year. See addendum 2 for work required due to this building not being constructed. |
RFI #: 6 | QUESTION: Drawing E200, keyed note 2. indicates installing heat trace in gutters and down spout. Please provide information on gutter and down spout lengths in order to provide accurate pricing. | ADDENDUM #: | ANSWER: Provide 120V, 20A Frost King Roof and Gutter Deicing cable. to cover the lengths of roof specified. Curve 1 should require one receptacle circuit and one 120ft cable. Curve 19 will require a minumum of 2 circuits, and 2 160ft cables. EC to field measure and confirm both roofs, once final construction is complete. Cable is for gutter and downspout only. No roof coverage is required. |
RFI #: 7 | QUESTION: In EC Procured items section of Drawing E002, the EC is to procure and run Cat 5E from theatrical Controller to each DMX box. Please indicate how we are to run the cable. | ADDENDUM #: | ANSWER: See RFI-003 answer. |
Below is a list of RFI questions submitted, along with accompanying answers for Contract Number: MVH.24.006.140 |
|||
RFI #: | QUESTION: | ADDENDUM #: | ANSWER: |
RFI #: 1 | QUESTION: Spec section 051200 paragraph 1.1 B refers to Sections 053100, 05500, 099113 and 099123. These spec sections are not included in the bid documents. Please provide these spec sections and a coating schedule if they apply to contract work. | ADDENDUM #: | ANSWER: Sections 053100, 05500, and 099123 are not in the scope of this contract. Spec section 051200 updated to remove references to the aforementioned sections. |
RFI #: 2 | QUESTION: Is this contract responsible for the supply of any structural steel framing materials specified in spec section 05120? | ADDENDUM #: | ANSWER: The only prepurchased owner-furnished items are the glulams and steel braces. All other items are in this contract. |
RFI #: 3 | QUESTION: Is this contract responsible for field touch up primer paint of areas defined by spec section 05120 paragraph 2.10 A? If yes, please provide shop drawings showing the areas that will be delivered unprimed. Will the structural steel material supply contract supply the touch up paint? | ADDENDUM #: | ANSWER: Owner will provide touch-up paint for field touch-up. |
RFI #: 4 | QUESTION: Spec section 052100 paragraph 2.9 refers to galvanizing. Is any of the structural steel supplied in this contract galvanized? If yes, please provide a coating schedule. | ADDENDUM #: | ANSWER: It is not galvanized, it is primer. All primer provided under previous contract. |
RFI #: 5 | QUESTION: Work under spec section 074600 Poly-Ash Trim does not appear to be included in the contract plans. Does spec section 074600 apply to this contract? If yes, provide plans and details. | ADDENDUM #: | ANSWER: Will be part of the stacked fascia. Refer to details 1 & 3, A250. |
RFI #: 6 | QUESTION: Spec section 074600 paragraph 1.02 refers to spec sections 07900 and 099113. These spec sections are not included in the bid documents. Please provide these spec sections, plans, details and painting schedules if the apply to work in this contract. | ADDENDUM #: | ANSWER: 079000 has been removed as a reference spec. 099113 is included in Addendum 1. |
RFI #: 7 | QUESTION: Spec section 074600 paragraph 3.03 H refers to section 099000. This spec section is not included in the contract documents. Please provide the specification and a painting schedule if it applies to contract work. | ADDENDUM #: | ANSWER: Spec section 099000 is not included in this scope. Spec will be updated in forthcoming addendum. |
RFI #: 8 | QUESTION: Spec section 074646 Fiber-Cement Siding does not appear to be included in the contract plans. Does spec section 074646 apply to this contract? If yes, provide plans and details. | ADDENDUM #: | ANSWER: Section 07 46 46 not in scope. |
RFI #: 9 | QUESTION: Spec section 074646 paragraph 2.01 B5 refers to section 099113. This spec section is not included in the contract documents. Please provide the specification if it applies to contract work. | ADDENDUM #: | ANSWER: Section 07 46 46 not in scope. |
RFI #: 10 | QUESTION: Spec section 076200 paragraph 1.02 refers to Sections 077100 and 079200. These spec sections are not included in the bid documents. Please provide. | ADDENDUM #: | ANSWER: 077100 should be 077200 and is issued in Addendum 1. 079200 is also included in Addendum 1. |
RFI #: 12 | QUESTION: Who is responsible for unloading the Glulam and Steel materials that are furnished under a separate contract? | ADDENDUM #: | ANSWER: This contract is responsible for unloading the Structural Steel and Glulams furnished by a prior contract. |
RFI #: 13 | QUESTION: Please confirm baseplates will be furnished with anchor bolts and holes to allow for grout installation. | ADDENDUM #: | ANSWER: Anchor bolts will not be furnished and are the responsibility of this contract. |
RFI #: 14 | QUESTION: Please confirm all bolted connections required for glulam and steel connections will have materials (bolts, nuts, washers) furnished under separate contract. | ADDENDUM #: | ANSWER: Materials (bolts, nuts, washers) are the responsibility of this contract. |
RFI #: 15 | QUESTION: Please provide the location of any and all grade beams on plan view drawings of each curve. None are shown. | ADDENDUM #: | ANSWER: A grade beam is shown at Curve 10. |
RFI #: 16 | QUESTION: Please confirm that the Micro Pile anchor plates will be furnished by others. | ADDENDUM #: | ANSWER: Yes, plates are provided by the pile installation contract. |
RFI #: 17 | QUESTION: Please confirm if ALL Glulam materials will be furnished by others. Including any wedges or other sections besides the beams. | ADDENDUM #: | ANSWER: Glulams and wedges shown on Curve 10 provided under previous contract. |
RFI #: 18 | QUESTION: Please confirm that glulam materials will be furnished with the required staining and sealing. | ADDENDUM #: | ANSWER: Confirmed |
RFI #: 19 | QUESTION: Please add Glulam beams 4, 5, A, B, C, D, E to bid breakdown form. | ADDENDUM #: | ANSWER: Please attach your requested breakout to original bid form. |
RFI #: 20 | QUESTION: Please provide additional information regarding the specified demolition. Photos, record drawings, etc. | ADDENDUM #: | ANSWER: Refer to sheet D100 for demolition scope. |
RFI #: 21 | QUESTION: Please confirm that the steel beam on curve 10 is to be furnished under this contract, but the two (2) connecting columns are to be furnished by others. | ADDENDUM #: | ANSWER: Steel beam on Curve 10 is provided under the Glulam and Steel Procurement contact. |
RFI #: 22 | QUESTION: Downspouts appear on bid breakdown, but are not shown on any drawings, please clarify. | ADDENDUM #: | ANSWER: Update plans to include Curve 1, 10, 19 forthcoming |
RFI #: 23 | QUESTION: Please provide a minimum compressive strength for concrete to be utilized in pile caps and piers. | ADDENDUM #: | ANSWER: 4500psi, max water/cement ratio of 0.45 |
RFI #: 24 | QUESTION: Detail on S-304 shows a gap underneath the gradebeam. Please confirm if this is correct, if so, provide dimensions. If possible, provide the reasoning, so that contractor can provide alternative options that improve constructability. | ADDENDUM #: | ANSWER: Provide 3" clear under grade beam. Temporary formwork may be provided. |
RFI #: 25 | QUESTION: Section #3 on sheet S301 as well as micropile sections on same sheet show top and bottom reinforcing for micropile caps but detail #1 PC-3 on sheet S302 only shows pile cap reinforcing centered over micropiles. Is additional SW and LW reinforcing required in pile cap#3? If so can the pile cap detail be updated to show reinforcing similarly to the other pile cap details on sheet S302. | ADDENDUM #: | ANSWER: Bars shown should be top and bottom. |
RFI #: 26 | QUESTION: Will the Glulam beams come with the bolt holes already pre-drilled? | ADDENDUM #: | ANSWER: Yes |
RFI #: 27 | QUESTION: Will the structural steel components arrive preassembled (Channel pieces and HSS columns bolted together)? | ADDENDUM #: | ANSWER: At this time it has not been confirmed what pieces if any will be preassembled. |
RFI #: 28 | QUESTION: Will this contract include any soil and erosion control, or will that be performed under a separate contract? | ADDENDUM #: | ANSWER: To be included |
RFI #: 29 | QUESTION: Specification section 05 12 requires plate washers for anchor bolts to be welded to base plates. Can a weld detail please be provided. | ADDENDUM #: | ANSWER: They do not require welding. |
RFI #: 30 | QUESTION: Specification section 03 32 does not list a required rebar coating. Is the contracts intent black bar? | ADDENDUM #: | ANSWER: Yes |
RFI #: 31 | QUESTION: Section 01 10 00 SOW, Part 1.3A (pg174/753) notes there is a “project schedule” in Section 00 31 13 Reference Summary Project Schedule Please provide the “Summary Project Schedule” and “Bid Milestones” that state they’re included in Section 00 31 13 (pg82/753). Please provide latest version of CPM Schedule w/ activities (inclusive of other concurrent bid/work packages) and anticipated durations Please provide “Critical Milestone” dates referenced in Article 13 (but not included) of the General Conditions (per section 00 31 13B) | ADDENDUM #: | ANSWER: See bid milestone schedule in Addendum #1. |
Below is a list of RFI questions submitted, along with accompanying answers for Contract Number: MVH.24.006.130 |
|||
RFI #: | QUESTION: | ADDENDUM #: | ANSWER: |
RFI #: 1 | QUESTION: Is the Bid date time of 11:00 P.M. correct? | ADDENDUM #: | ANSWER: The Bid time will be 11:30 AM. This will be corrected in the addendum 1. |
RFI #: 2 | QUESTION: Plan sheet C540 pipe trench detail note 5 states a minimum cover of 5' for water and sanitary force mains and on C560 pipe trench detail note 5 states 6' minimum cover on watermains. Can the owner please clarify. | ADDENDUM #: | ANSWER: C560 for sewer/water. C540 is for storm only. Changes to the detail notes will be clouded in Addendum 01. |
RFI #: 3 | QUESTION: Plan sheets matchlines do not match up and some have over laps. This makes it difficult to accurately perform a takeoff when plan sheets matchlines are incorrect. Can the owner please address matchlines. | ADDENDUM #: | ANSWER: Match lines will be addressed in Addendum 01. |
RFI #: 4 | QUESTION: On plan sheet C142, there areas to be numerous drainage fingers in the Heart location that are not labeled for size. Can the owner please clarify. | ADDENDUM #: | ANSWER: Sizes will be labeled in Addendum 01. |
RFI #: 5 | QUESTION: Typical site utilities practices are to connect or leave utility connection 5 feet from building foundation. Please clarify where the site utilities are to stop and the building picks up utility. | ADDENDUM #: | ANSWER: Site utility practices are to connect or leave utility connection 5ft from building foundation where the building picks up the utility. |
RFI #: 6 | QUESTION: Can the owner specify the size of future water services on plan sheets C154, C155. Detail for these services states 1" or 2", to accurately estimate we need clarification on sizing for each service. | ADDENDUM #: | ANSWER: All future water services on plan sheets C154 and C155 will be 1" unless otherwise noted. |
RFI #: 7 | QUESTION: Plan Sheet C155 has two future water services near station 21+75 and 25+10, please provide detail for these services. They seem to imply a 4x4x4 tee and then transition to 1" or 2" service but fittings or sizing is not specified. | ADDENDUM #: | ANSWER: Refer to Detail 2 C560 which indicates the use of a corporation stop and service saddles (Service saddles for working pressures up to 350 psi by Mueller, Romac or approved equivalent). |
RFI #: 8 | QUESTION: Can the owner please clarify if non-metallic sections of watermain is to be C900 bell and spigot or HDPE welded pipe? | ADDENDUM #: | ANSWER: All non-metallic sections of watermain are to be heat fused (DR-9 or DR-7) HDPE pipe as indicated on the plans and specs. |
RFI #: 9 | QUESTION: Due to the nature of Lump sum bids and the size and scope of the project we respectfully request a 2 week extension to prepare bid. | ADDENDUM #: | ANSWER: We do not intend to extend the bid date at this time. |
RFI #: 10 | QUESTION: On plan sheet C152 a section of the watermain is labeled for insulation per detail 7 on C560, then on the profile view on C182 detail 8 on C560 is referenced. Please clarify. | ADDENDUM #: | ANSWER: Refer to Detail 8 C560. |
RFI #: 11 | QUESTION: Can the owner please identify the location and size of the Hydrodynamic Separator? | ADDENDUM #: | ANSWER: Unit is outlined in the SWPPP which has been included with this bid. 1,104 CF WQv, 0.77 CFS flow rate. Contech Cascade CS-4. |
RFI #: 12 | QUESTION: Plan Sheet C141 references a split box culvert, can a specification section and detail be provided for this structure? Is the intent of culvert being split to allow other contractor to install ammonia lines before installation of top sections of box? | ADDENDUM #: | ANSWER: The box culvert and all ammonia piping work is under separate contract and will be coordinated via site construction management. |
RFI #: 13 | QUESTION: Please provide Invert elevations for proposed 8'x6' Box Culvert. | ADDENDUM #: | ANSWER: The box culvert and all ammonia piping work is under separate contract and has been positioned to allow for all utilty work under this contract to be performed as shown on plans. |
RFI #: 14 | QUESTION: Based on the question #5 and answer provided, will the booster pump and associated interior plumbing, expansions tanks be removed from this contract and included in building contracts? | ADDENDUM #: | ANSWER: No, this scope remains within this contract and should be included in this bid. |
RFI #: 15 | QUESTION: The retaining wall details on plan sheet C-510 show walls D, F, and H being backfilled with 3/4" drainage stone. The profile sheets show walls B and C being backfilled with 3/4" drainage stone and 2" washed stone, however there are no details shown for walls A, E, G, I, J and K. Please advise as to the backfill scenario for these 6 walls. | ADDENDUM #: | ANSWER: Plans have been updated to clarify stone backfill requirements. |
RFI #: 16 | QUESTION: Will the 1932 bobsled track be demolished at the precast split box culvert shown on drawing C-131. If the track is not demolished, provide details of the controlled removal and reinstallation of the 1932 bobsled track or other means of resolving this conflict. | ADDENDUM #: | ANSWER: No, this section of the track is historic and will require temporary shoring and protection while work is performed. Please note that the box culvert scope is not in this contract. |
RFI #: 17 | QUESTION: Will the Cliffside Coaster be removed and reinstalled for the installation of the precast split box culvert shown on drawing C-131. If yes, provide plans, details and specifications for the Cliffside Coaster. If no, provide details of how this conflict will be resolved. | ADDENDUM #: | ANSWER: A portion of the Cliffside Coaster will need to be removed and reinstalled. Select drawings from the initial Mt Coaster Installation will be provided for reference in the next addendum. |
RFI #: 18 | QUESTION: On drawing C-132 it appears that the continuation of the precast spit box culvert shown on drawing C-131 extends to end below a new roof structure foundation. The foundations include micropiles that will conflict with the installation of the precast. Provide details of how this conflict will be resolved. | ADDENDUM #: | ANSWER: The 1932 (1980) bobsled track section is designated as historic. The Contractor should provide temporarily supports for the structure during excavation under the track. |
RFI #: 19 | QUESTION: Note on plan sheet C141 states that the ammonia line relocation is by others. Does that include the removal of the existing lines to allow for the installation of the precast spit box culvert shown on C-131? When will the relocation by others of these ammonia lines take place? | ADDENDUM #: | ANSWER: The demolition of ammonia pipe, installation of box culvert and all ammonia piping repair, relocation and installation will be done by others. |
RFI #: 20 | QUESTION: Provide a detail of the ends of the precast split box culvert for the ammonia line penetrations. | ADDENDUM #: | ANSWER: Culvert is under separate contract. |
RFI #: 21 | QUESTION: In Addendum #1, the time is listed as 11:30AM on the Notice to Bidders while everything else says 11:00AM. We would just like to confirm that the bid is due at 11:00AM. | ADDENDUM #: | ANSWER: The Bid time will be 11:30 AM. |
RFI #: 22 | QUESTION: Can the owner provide the working water pressures that will be experienced at the tapping valve location. | ADDENDUM #: | ANSWER: Working pressure at the tapping valve location is approximately 70 psi. The existing WTP pumps operate at a discharge pressure of approximately 67 psi @ FFE 2,069 feet. |
RFI #: 23 | QUESTION: Due to the recent addendum #1 and the volume of changes to the utility work, earth work, finishes and questions that have not been addressed thus far we respectfully request a two week extension to account for changes. | ADDENDUM #: | ANSWER: the bid date will not be extended. |
RFI #: 24 | QUESTION: While reviewing the utility plans, it appears that the waterline running parallel to the bobsled track does not include inline valves. We would like to confirm whether this should be bid as specified, without inline valves. | ADDENDUM #: | ANSWER: Inline valves should be provided every 500 linear feet. |
RFI #: 25 | QUESTION: Due to the limited access in this area, the nature of the utility work, and its location as shown on the plans, along with the multiple contracts being executed in this relatively small space, we would like to request clarification on the access requirements. Specifically, what type of access will need to be available throughout the workday and at the end of each shift? | ADDENDUM #: | ANSWER: One lane of vehicle access will be required throughout the project site from 7:00 AM to 3:00 PM daily. |
RFI #: 26 | QUESTION: What are the required storage volumes for the four (4) underground stormwater systems specified? | ADDENDUM #: | ANSWER: The required storage volumes are provided in the SWPPP which was included in the bid docs. |
RFI #: 27 | QUESTION: Are there required minimum footprints for the four (4) underground stormwater systems specified, or can a smaller footprint be proposed with equivalent storage? | ADDENDUM #: | ANSWER: Yes, there are required minimum footprints as outlined in the SWPPP. |
Below is a list of RFI questions submitted, along with accompanying answers for Contract Number: MVH.24.006.160 |
|||
RFI #: | QUESTION: | ADDENDUM #: | ANSWER: |
RFI #: 1 | QUESTION: Per the Instructions to Bidders, a pre-bid conference and site visits are typically held with the date, time and location disclosed in the Notice to Bidders. The Notice to Bidders indicates a pre-Bid will be held on January 30th, 2025, at 10:00 AM. Details pertaining to the location or whether this pre-bid is virtual are not included in the Notice to Bidders. Please provide details on the pre-bid. | ANSWER: The Pre-bid meeting will be held at the Mountain Pass Lodge at Mt Van Hoevenberg. 31 Van Hoevenberg Way Lake Placid, NY 12946. The Prebid meeting will be available to attend virtually on Teams at the link below. Tour of the project site will be available after the meeting. Microsoft Teams: Meeting ID: 296 739 523 67 Passcode: 6Kb9T47p Dial in by phone +1 716-371-1579,,336553816# United States, Niagara Falls Phone conference ID: 336 553 816# |
|
RFI #: 2 | QUESTION: Please provide Masonry Specs. | ANSWER: Masonry Specification issued with Addendum 1. |
|
RFI #: 3 | QUESTION: Please provide civil drawings. | ANSWER: Civil scope is being performed under a separete contract. All civil plans and specifications will be available through ORDA procurement website this week. |
|
RFI #: 4 | QUESTION: Drawing S301 is Referencing Civil Plans. No Civil Plans have been received with Base Bid Documents. Please Clarify if Civil work is part of the Contract. | ANSWER: See response #3. |
|
RFI #: 5 | QUESTION: No Earthwork Sections are shown on table of Contents. If they pertain, please provide. | ANSWER: Earthwork Specification issued with Addendum 1. |
|
RFI #: 6 | QUESTION: Is there approved methods for dealing with Bedrock? (Rock Excavation Spec?) | ANSWER: Rock removal must be performed safely while the balance of work on the site is being executed. Contractor is also responsible to ensure the protection of adjacent infrastructure including the combo track and ammonia piping. The method of rock removal, and associated oversight and monitoring shall be reviewed and approved by ORDA. |
|
RFI #: 7 | QUESTION: Hardware Specs and Hardware Schedule 08 71 00 is missing also no hardware sets are indicated on the Door schedule. | ANSWER: This scope has been removed from the contract. Refer to Addendum 2 and forthcoming Addendum 3. |
|
RFI #: 8 | QUESTION: Please Clarify the Extent of Glulam Material that is being provided by Previously Awarded Contracts And Clarify what this GC Package will need to Provide regarding Glulam Material for Start 1 & Start 3 (Drawing would Help) | ANSWER: This scope has been removed from the contract. Refer to Addendum 2 and forthcoming Addendum 3. |
|
RFI #: 9 | QUESTION: Please Clarify what Material being provided by Previously Awarded Contract will need to be installed by the GC Package (Drawing would help) | ANSWER: This scope has been removed from the contract. Refer to Addendum 2 and forthcoming Addendum 3. |
|
RFI #: 10 | QUESTION: Please Clarify What if Any Connector Plates/Anchor Bolts are to be provided to GC for Installation of any material provided by previously awarded contract | ANSWER: This scope has been removed from the contract. Refer to Addendum 2 and forthcoming Addendum 3. |
|
RFI #: 11 | QUESTION: Please Clarify Extent of Steel work provided by Previously Awarded Contract That would need to be installed by GC. | This scope has been removed from the contract. Refer to Addendum 2 and forthcoming Addendum 3. | |
RFI #: 12 | QUESTION: Please Clarify what if any Connector Plates/Anchors bolts need to be provided by GC to Install any Steel Provided by others. | ANSWER: This scope has been removed from the contract. Refer to Addendum 2 and forthcoming Addendum 3. |
|
RFI #: 13 | QUESTION: Please Clarify Scopes of work of contracts that pertain to anything related to Start 1 & 3. | ANSWER: This scope has been removed from the contract. Refer to Addendum 2 and forthcoming Addendum 3. |
|
RFI #: 14 | QUESTION: Please Clarify what Sitework if any the GC will own for this Package Who is responsible for Bedrock (Drawing would help) | See response #3. Sitework is being provided under a separate contract. | |
RFI #: 15 | QUESTION: On drawing E-100 page 1669 can you provide more detail on what the Village of Lake Placid Electric Dept. scope of work is and what material if any they will be providing. | ANSWER: Village of Lake Placid will be replacing the old single phase transformers with new three phase transformers. |
|
RFI #: 16 | QUESTION: Start 1 Building: 1. Reference drawing S110, Please provide the base plate type for column G/5. 2. Reference drawing S110, Stair between grid lines G to J and 5 to 6 is called out as wood framed. The same stair shown on plan 1/A500 is called out as a concrete filled steel pan stair. Please clarify which is correct. 3. Reference drawing S120, plan 2/S120, Please provide missing beam size for beam online B, between 2 and 4. | ANSWER: 1. BP-4; 2. Follow structural drawings (wood); 3. W18x35 |
|
RFI #: 17 | QUESTION: Start 3 Building: 1. Drawing A402 is listed on the Index of Drawings list for start 3 building. This drawing was not included in the bid set of drawings. Please issue this drawing. | ANSWER: This scope has been removed from the contract. Refer to Addendum 2 and forthcoming Addendum 3. |
|
RFI #: 18 | QUESTION: Can you confirm that only (1) copy of the bid form needs to be submitted. Or, do you want (2). Does the newly added Contractor breakdown need to be submitted on bid day? | ANSWER: Per Document 00 21 13 Instructions to Bidders, Section 6 Submission of Bid, Part 6.1 submit the original and one (1) copy of the items identified in Section 4.14 in a sealed envelope. Section 4 Preparation of Bid, Part 4.14 lists the items to be submitted in duplicate. Per Document 00 21 13 Section 13 Mandatory Post-Bid/Pre-Award Subittal Requirements, Part 13.2.3 the detailed Cost Estimate is to be included in the pre-award submittal package within two business days of bid opening. |
|
RFI #: 19 | QUESTION: We would like to confirm the scope of work for the construction of Building 1. Specifically, we seek clarification that the scope includes the building envelope, as well as the foundation and substructure. | ANSWER: The building evelop is not included in this contract. |
|
RFI #: 20 | QUESTION: We would like to confirm the scope of work for the construction of Building 1. As there are no civil plans available at the time of this RFI, we understand that all site utilities are not to be included in this contract. | ANSWER: The full civil drawings are availavlbe as reference as part of the Site Utilities and Finishes bid docs. |
|
RFI #: 21 | QUESTION: Requesting confirmation regarding the availability of a civil drawing set for the construction of Building 1. Specifically, we would like to confirm whether civil drawings will be provided for this site. | ANSWER: The full civil drawings are availavlbe as reference as part of the Site Utilities and Finishes bid docs. |
|
RFI #: 22 | QUESTION: We would like to confirm the scope of work for the construction of the Start Building 3 site. Specifically, we seek clarification that the scope includes the building foundation and substructure, but does not incorporate the building envelope within this contract. | ANSWER: The building envelop is not in this contract. |
|
RFI #: 23 | QUESTION: We would like to confirm the scope of work for the construction of Building 3. As there are no civil plans available at the time of this RFI, we understand that all site utilities are not to be included in this contract. | ANSWER: Water and sewer utlities shall be installed below the slab, and extended 10' outside of the limits of the foundation. |
|
RFI #: 24 | QUESTION: We kindly request confirmation regarding the availability of a civil drawing set for the construction of start building 3. Specifically, we would like to confirm whether civil drawings will be provided for the site. | ANSWER: The full civil drawings are availavlbe as reference as part of the Site Utilities and Finishes bid docs. |
|
RFI #: 25 | QUESTION: We would like to confirm the scope of work for the construction of the Timing Building. Specifically, we seek clarification that the scope includes the building foundation and substructure, but does not incorporate the building envelope within this contract. | ANSWER: The building envelop is not in this contract. |
|
RFI #: 26 | QUESTION: We would like to confirm the scope of work for the construction of the Timing Building. As there are no civil plans available at the time of this RFI, we understand that all site utilities are not to be included in this contract. | ANSWER: Correct, site utilities not included. |
|
RFI #: 27 | QUESTION: We kindly request confirmation regarding the availability of a civil drawing set for the construction of the Timing building. Specifically, we would like to confirm whether civil drawings will be provided for the site. | ANSWER: A civil site plan was added to this plan set. The full civil drawings are currently available as reference as part of the Site Utilties and Finishes bid docs. |
|
RFI #: 28 | QUESTION: Scope of work for Start 1 building: earthwork only within building footprint, demolition, concrete foundation and concrete slabs, structural steel install only, misc. steel labor and material, rough carpentry, glued laminated materials install only, finish carpentry, foundation waterproofing, roofing, painting, electrical. Please confirm. | ANSWER: Start 1 includes all scope shown on plans, with the exception of site utilties and finishes which are currently being procured under active bid of MVH.24.006.130. |
|
RFI #: 29 | QUESTION: Scope of work for Start 3 building: earthwork only within building footprint, concrete foundation. Please confirm. | ANSWER: Water and sewer utlities shall be installed below the slab, and extended 10' outside of the limits of the foundation. |
|
RFI #: 30 | QUESTION: Scope of work for Timing and Operations building: earthwork only within building footprint, concrete foundation. Please confirm. | ANSWER: Confirmed. |
|
RFI #: 31 | QUESTION: Please provide site drawings showing grading and site elevation for buildings Start 1, Start 3, and Timing and Operations building. | ANSWER: Full site utilties and finishes contract documents are available for reference under active bid of MVH.24.006.130. |
Below is a list of RFI questions submitted, along with accompanying answers for Contract Number: MVH.24.006.203 |
|||
RFI #: | QUESTION: | ADDENDUM #: | ANSWER: |
RFI #: 1 | QUESTION: Can curved glulam beams at the canopy be 10 1/2" wide rather than 10 3/4" wide? | ADDENDUM #: 1 | ANSWER: Yes 10.5 inch is acceptable. |
RFI #: 2 | QUESTION: Please confirm location of glulam treated material. | ADDENDUM #: 1 | ANSWER: All exposed wood will receive the treatment specified. |
RFI #: 3 | QUESTION: Please confirm roof decking at the Canopy, Start Building 1 and Start Building 3 is not included in this portion of procurement. | ADDENDUM #: 1 | ANSWER: Correct: roof decking at Canopy, Start 1, and Start 3 is not included in this procurement package. |
RFI #: 4 | QUESTION: Is the glulam supplier required to supply structural steel? | ADDENDUM #: 1 | ANSWER: The awarded proposer will be resposible for providing both the structural steel and the glulams. |
RFI #: 5 | QUESTION: Please confirm glulam to steel connections will be detailed in construction documents. Can an example detail be shared at this time? | ADDENDUM #: 1 | ANSWER: Final details to be coordinated with glu-lam fabricator. Connection concepts shown in 1/S301 are designed to transmit required forces. The bolt pattern shown would require 7/8 inch galv A307 bolts. |
RFI #: 6 | QUESTION: Please confirm that A325 bolts referenced in 06 18 00 2.4 B can be disregarded (superseded by A307 bolts per 2.4 H). | ADDENDUM #: 1 | ANSWER: Steel to steel connections (2/S301) to utilize ¾ inch A325 galv bolts. |
RFI #: 7 | QUESTION: 'Is the supplier of this project responsible for installation? | ADDENDUM #: 1 | ANSWER: This contract is for the procurement of materials only. |
RFI #: 8 | QUESTION: 'Are bid bonds required for material suppliers to bid this project? | ADDENDUM #: 1 | ANSWER: Bid Bonds are required to be included with the proposal for this material procurement. |
RFI #: 9 | QUESTION: Are all the roofing materials included in this contract? Or just Glulam and steel? | ADDENDUM #: 2 | ANSWER: No this contract is only for the glulams and the structural steel to support the glulams. |
RFI #: 10 | QUESTION: Are the vertical columns shown on A251 as part of the details for "Type A, B, D, E" included in this contract? If so, what materials are they constructed out of? What are the sizes and dimensions? | ADDENDUM #: 2 | ANSWER: They match the sloping HSS |
RFI #: 11 | QUESTION: Does this contract include unloading of materials? | ADDENDUM #: 2 | ANSWER: Due to the Project Labor Agreement, this contract does not include unloading of material. |
RFI #: 12 | QUESTION: Does this contract include storage of materials on-site? | ADDENDUM #: 2 | ANSWER: Due to the size of the overall project, only limited materials can be stored on site. Delivery cordination will be required. |
RFI #: 13 | QUESTION: Regarding RFI 0005 and 0006 the version of S301 in the project manual/procurement documents does not show any glulam bolts in section 1 and there is no section 2 shown. Please provide a copy of S301 that includes this information. | ADDENDUM #: 2 | ANSWER: This information was added on subsequent issuance when SOW expanded beyond glu-lam beam procurement. |
RFI #: 14 | QUESTION: In regards to RFI 0002 by "exposed wood" please clarify if that means all wood outside of a building envelope. So, only fully interior members at start 3 would be untreated? | ADDENDUM #: 2 | ANSWER: Update: all glulams to be untreated, with surface applied sealers only regardless of location/exposure. |
RFI #: 15 | QUESTION: Spec section 06 18 00 paragraphs 2.2 B and C indicate the use of Douglas Fir or Southern Pine 24F-1.8E. Tridome Structures proposes the use of species suited for the application that are as locally available as possible to the site. In this case, we are looking to use Spruce Pine Fir South (SPF-S). SPF-S includes several species of Spruce readily available in the US Northeast where both the project and Tridome's manufacturing facilities are located. Neither Douglas Fir nor Southern Pine are species native to the Lake Placid region. This substitution maintains the structural performance and increases the architectural aesthetic compared to the species indicated in the project specifications. The specified product is DF/SP and our alternative is SPF with 85% of the raw material being sourced from New England. | ADDENDUM #: 2 | ANSWER: Local species is ok so long as strength and elasticity requirements are met (Fb=2400psi, E=1800ksi) |
RFI #: 16 | QUESTION: RFI Answers 5 and 6 in addendum 1 refer to connection details 1/S301 and 2/S301 respectively. These details are not included on sheet S301 of the contract plans. Please provide these details. | ADDENDUM #: 2 | ANSWER: See updated drawing S301.1 |
RFI #: 17 | QUESTION: Is the supplier of Glulam and/or Steel responsible for any connection details or will these be provided by ORDA? If provided by ORDA, provide the date that they will be made available. This date is crucial to allow the supplier to fill out bid form 00 21 01 Time Schedule Form. | ADDENDUM #: 2 | ANSWER: See updated drawing S301.1 |
RFI #: 18 | QUESTION: In order to fill out bid form 00 21 01 Time Schedule Form, provide the following dates/durations. 1. Award date? 2. Date ORDA will provide final construction drawings including connection details to the supplier? 3. ORDA shop drawing review duration for Curves 17 & 20? 4. ORDA shop drawing review duration for Curves 14 & 19? 5. ORDA shop drawing review duration for Curves 1,4 & 10? 6. Date ORDA will provides final detail and connection drawings for the Start 1 and Start 3 Buildings as shown on drawings S120, S121 & S200? 7. Date ORDA will have construction drawings for the Spectator and Sport Services Building Glulam? | ADDENDUM #: 2 | ANSWER: 1. ORDA is targeting an award in mid February. 2. Final documents will be provided for the base bid items prior to proposals being due. 3,4,5. We hope to be able to turn the shop drawings for the curves around in a few days. 6. See updated drawing S301.1. 7. Due to the nature of the design of this building, shop drawings and delivery date will be negotiated after the award. |
RFI #: 19 | QUESTION: Does the Final Date To Deliver Remaining Structural Steel & Glulam as shown on bid form 00 21 01 include the allowance Spectator & Sport Services Building Glulam? If it is included, provide a scope of work. | ADDENDUM #: 2 | ANSWER: The amount and delivery date for the Spectator & Sports Service Building will be negotiated and issued as a Field Order. |
RFI #: 20 | QUESTION: Specifically state what scope of work (material supply) is included in the bid form item 00 21 02 Amount To Be Invoiced At Deliver Remaining Structural Steel & Glulam. | ADDENDUM #: 2 | ANSWER: See Document 00 21 02 - Payment Schedule Form - Addendum #2. |
RFI #: 21 | QUESTION: What elements will require “mockups” as detailed in section 01 43 39? | ADDENDUM #: 2 | ANSWER: Typical steel bracing and glulam after surface applied sealer shall constitute the mockup. |
RFI #: 22 | QUESTION: Overall Contract Scope – Provide written summary of work to be performed. With multiple contracts interfacing as part of the overall program, it would be beneficial to have a more detailed breakdown of what is part of this contract, and what is NIC. | ADDENDUM #: 2 | ANSWER: The scope of work is the fabrication and delivery of the structural steel support and glulams shown in the contract drawings. All foundations and erection of the structures will be by others. |
RFI #: 23 | QUESTION: What is the base plate and anchor bolt design/designations for the double C15x33.9 and HSS 16” supports? Reference drawing S300. | ADDENDUM #: 2 | ANSWER: See Detail 5, Drawing S301.1 |
RFI #: 24 | QUESTION: Please provide sketch of the “saddle tie plate” that is welded to the HSS 16x10 that supports the glulam. Reference drawing A251. | ADDENDUM #: 2 | ANSWER: See Detail 1, Drawing S301.1 |
RFI #: 25 | QUESTION: Per spec section 051200, there is reference to an exterior paint specification. Since the steel is exposed to view, what is the required shop finish of the structural steel channels and HSS? | ADDENDUM #: 2 | ANSWER: SSPC-SP6 blast prep and cold galvanizing to accept a high-performance epoxy or urethane finish system. |
RFI #: 26 | QUESTION: Per drawing S300.1, the column supports on the left hand side of each detail that support the opposite end of the curved glulam appear to be HSS columns. Please advise. If they are HSS columns, please provide base plate and anchor bolt design/designation for these columns. | ADDENDUM #: 2 | ANSWER: They match the sloping HSS. |
RFI #: 27 | QUESTION: It appears that the ORDA’s Insurance Requirements and Additional Insured document (referenced in Article 19 of the General Conditions) that lists the required insurance limits is missing from the project manual. Please advise. | ADDENDUM #: 2 | ANSWER: As this contract is for materials only with no onsite work being performed, no Insurance Requirements are necessary. |
RFI #: 28 | QUESTION: An HSS 16x10 does not exist. Please verify what HSS size to use and if any connection changes will occur, ie fill plates etc? | ADDENDUM #: 2 | ANSWER: HSS 14x10 is acceptable. |
RFI #: 29 | QUESTION: On drawing S200, Start #3 there appears to be structural framing for a walking surface at Elevation 0’-0”. Is this new or existing? There is a similar situation on drawing S301, Start #1. | ADDENDUM #: 2 | ANSWER: The walking surface is new, but is not included in this material procurement contract. |
RFI #: 30 | QUESTION: Regarding structural tube availability; tube sizes 16x10x5/8 and 16x10x1/2 are not readily available (or produced). Similar sizes such as 14x10, 16x12, 16x8, in 1/2” or 5/8” wall thickness could be available with mill rollings scheduled to take place in February. Please clarify/confirm the the required column size(s) for this project. | ADDENDUM #: 2 | ANSWER: HSS 14x10 is acceptable. Wall thickness as currently noted. |
Below is a list of RFI questions submitted, along with accompanying answers for Contract Number: MVH.24.006.120 |
|||
RFI #: | QUESTION: | ADDENDUM #: | ANSWER: |
RFI #: 1 | QUESTION: Steel pipe is classified and sized by Outside Diameter, O. D. Not I. D. as called for 1.8 B 1. and 2.1 C 3. PLease clarify what OD is required? | ANSWER: 6.625 or 7 inch OD both acceptable for use. |
|
RFI #: 2 | QUESTION: EPOXY Coating: 2.1 D 1. What gets painted the pipe the rebar or both? I suggest using a 10' starter casing with the upper 5' painted and the lower 5' left bare to bond to the rock. Does rebar get painted? | ANSWER: Epoxy coating is not required. |
|
RFI #: 3 | QUESTION: Section 31 63 33 - 3.2 B " Percussion-type drilling equipment is not permitted." This will cut production in 1/2. Is this what you want? FYI micropiles and tiebacks are installed with double head rigs, rotary on the casing pipe and percussion (hammering) on the rock with the internal (removable) drill string. I suggest modifying your specs or using NYSDOT specs not intermixing them. | ANSWER: Bid in accordance with the specifications. |
|
RFI #: 4 | QUESTION: Where are the load tests and how many are their both Tension and Compression? | ANSWER: The load test procedure shall be proposed by the contractor and accepted by the Geotechnical Engineer. The procedure shall apply 200 percent of the design load to each of the pile types on at least one pile. A 3 pile set-up with reaction piles and hydrualic jacks is anticipated and the piles shall be tested in tension and compression. |
|
RFI #: 5 | QUESTION: Are you going to specify the number of drill rigs you want as 500 piles in 5 months on this site is very aggressive? | ANSWER: We are not dictating means and methods. We have provided the number of micropiles we expect and the expected date of completion of the micropiling installation. It is incumbent of the contractor to staff the project appropriately for the expectations outline in the project manual. |
|
RFI #: 6 | QUESTION: There is no structural details/count for the micropiles at Curve 20 in the structural drawing set. Please provide. | ANSWER: Plans included in Addendum #2 have been updated to include Curve 14 and Curve 20 micropiles. |
|
RFI #: 7 | QUESTION: 'Specification 316333 section 3.2B “…Percussion-type drilling equipment is not permitted…” Subsurface conditions include hard glacial till, cobbles, boulders and hard rock (gneiss) drilling. Rotary drilling methods would include utilization of re-circulation polymer slurry, slurry pumps, de-sanding equipment and roller bit tooling. The subsurface conditions coupled with these drill methods and winter work in the Adirondacks will result in the most onerous and low production drilling imaginable. Please consider use of industry standard percussive (pneumatic) drilling methods. | ANSWER: Please see the response to RFI #3. |
|
RFI #: 8 | QUESTION: 'Please provide a pile plan for Curve 20 similar to what was provided for the other work areas. | ANSWER: See Addendum #2. |
|
RFI #: 9 | QUESTION: 'Anticipated utilities present at the site include storm, sanitary, electric, fuel, ammonia and other. Please provide a pile plan depicting utility locations with respect to the piles. | ANSWER: Pile Layout Drawings contain known locations of utilities, it is the responsibility of the contractor to confirm utilities locations in work areas. Final layout will be approved before start of construction. |
|
RFI #: 10 | QUESTION: 'Please specify the quantity and general location of pile load tests that will be required. | ANSWER: Please see the response to RFI #4 |
|
RFI #: 11 | QUESTION: 'Please provide micropile cut-off elevations. | ANSWER: Piles shall terminate at existing grade with grout held down to 2 feet below grade. Final cut to be performed by pile cap contrator under separate project. |
|
RFI #: 12 | QUESTION: 'Please provide a schedule of when drilling operations will be dis-allowed due to various events. | ANSWER: Reference project schedule has been updated with additional information found in Addendum #2 |
|
RFI #: 13 | QUESTION: 'Boring indicate high variation in depth to bedrock, this directly impacts the payment item of micropiles which is linear feet. Please consider amending payment items to include a “per each” and a linear feet. This would reduce the risk of significant variation between the bid value and payment value of the micropile work. | ANSWER: The intention for the linear feet unit price for the micropile is due to the variations in the boring depths. |
|
RFI #: 14 | QUESTION: 'Is micropile reinforcement required to be epoxy coated (316333 sections 2.1.D.1)? This would be non-standard. | ANSWER: epoxy coating of reinforcing is not required. |
|
RFI #: 15 | QUESTION: 'Is micropile reinforcement required to be encapsulated (316333 section 2.1.D.3)? This would be non-standard. | ANSWER: encapsulation is not required. |
|
RFI #: 16 | QUESTION: 'Spec Section "31 63 33 Drilled Micropiles - 1.7 - I" requires the performance of a precondition survey. Please provide a detailed list of structures/features that are to be covered by this survey. Will actual field surveying be required? | ANSWER: Contractor is responsible for precondition survey, however it is anticpated that this shall include photo documentaiton of existing track structure and foundation elements exposed at and above grade adjacent to areas of work. Any damage observed after pile instalaltion not documented in the precondition survey shall be reapired at no cost to the Owner. |
|
RFI #: 17 | QUESTION: 'Can the missing Appendix files (I, J) be provided? | ANSWER: In Addendum 2, Exisiting conditions of the garage to be demolished have been added to Appendix I, and Appendix J has been removed. |
|
RFI #: 18 | QUESTION: 'Does (and if so how) Appendix K apply to this project? | ANSWER: Appendix K does apply as the scope of work includes work adjacent to ammonia lines |
|
RFI #: 19 | QUESTION: 'Structural Drawing Set: Please provide the bottom of pile cap elevation(s) for each pile cap. | ANSWER: Top of pile cap shall be at existing grade. Size of pile cap is shown on plans. |
|
RFI #: 20 | QUESTION: Section 316333-Drilled Micropiles - Please confirm the appropriate Buy America(n) provision for the project. It is our understanding that the micropiles installed for a government project shall require prime mill certifications for the steel. Is this required? Or can new mill secondary micropile casing be utilized, which does not have mill test reports for this material. In absence of a mill certificate, a letter is submitted from the supplier certifying that the manufactured and sourced domestically. Mechanical test certificates “coupon testing,” can be provided. | ANSWER: As per article 25.4 of document 00 72 13 - General Conditions; "The Contractor agrees, that if the value of this Contract exceeds $100,000 all structural steel, reinforcing steel and other major steel items to be incorporated in the Work of this Contract shall be produced and made in whole or substantial part in the United States, its territories or possessions." Also due to the nature of project, it is the Engineer Of Record and ORDA's expectation that new steel is provided with mill certifications for the steel. |
|
RFI #: 21 | QUESTION: 'Drawing C131, C132, C133, C134 do not have elevation number designations on the contour lines. Provide an updated drawing with elevation number designations for the contour lines. | ANSWER: See Addendum #2. |
|
RFI #: 22 | QUESTION: 'Structural Drawing Set: Please provide the top of micropile elevation(s) for each pile cap. | ANSWER: Draft: Please see the response to RFI #11 |
|
RFI #: 23 | QUESTION: 'Please confirm which building(s) are to be demolished as part of this contract. Please provide clear limits of demolition. Please provide pictures and as-built plans detailing the building's construction. | ANSWER: See pictures contained in Appendix "I" - Record Documents and Photographs Of Existing Conditions included in Addendum #2 |
|
RFI #: 24 | QUESTION: 'Sheet C-101 states that sediment and erosion control will be unit-price items and that estimated quantities will be provided. No quantities are listed, please provide. | ANSWER: Note has been updated on sheet C-101. |
|
RFI #: 25 | QUESTION: 'Sheet C-101 shows "Contractor Parking", Site Access Rd", "Laydown Area", "Office/Trailer" and "Construction Fence" in the legend; what if any scope of work is required under this contract for each of these items? | ANSWER: Contractor Parking: Initial grading of parking area for safe access. This may include but is not limited to filling in exiting potholes, grading areas that have eroded, etc. This scope also includes final grading and installation of stone as needed at the end of the project. Site Access Road: Maintenance of the Site Access Road over the course of construction which may include but is not limited to repairing areas damaged during construction. The site access spurs leading to the proposed laydown areas shall be constructed with a 6-inch thick layer of compacted subbase material on geotextile fabric. The scope also includes final repair of any damaged areas on the existing road. Laydown Area: Laydown areas shall be constructed with a 6-inch thick layer of subbase material on geotextile fabric. These areas shall be removed and restored to their original condition upon completion of the project. Office/Trailer: The proposed areas for the office/trailers shall be prepped with a level pad of 4-inch thick compacted sub base material. These areas shall be restored to their original condition upon completion of the project. Construction Fence: Fencing to be installed per linear foot and shall be 6-feet high post driven fence with a 12’-wide operable gate. |
|
RFI #: 26 | QUESTION: '"Appendix D" lists "Snow Removal", "Temporary Roads, Facilities, and Protection", and "Erosion & Sedimentation Controls Initial Install"; please confirm that scope of work for each of these items. | ANSWER: Snow Removal: Maintenance of roadways, walkways, and laydown areas during the winter months which includes removal of snow in these areas and salting/sanding as necessary to provide a non-slip surface for traversing. Please note that direct work areas will be the responsibility of the contractors. The snow removal is only for common areas on the project. Temporary Roads, Facilities, and Protection: Traffic control devices for roadway delineation and maintenance of the devices and access roads during the course of construction. Erosion & Sedimentation Controls Initial Install: Installation of various erosion and sediment control devices as necessary in the areas of disturbance for the logistics and pile installation scopes of work. |
|
RFI #: 27 | QUESTION: 'Is the field order allowance $1,000,000 or $100,000? Different amounts are listed in different areas. | ANSWER: See Addendum #1. |
|
RFI #: 28 | QUESTION: No "Curve 20 Plan" is provided in the sheet set. If this is an error, please provide the requested sheet. | ANSWER: See Addendum #2. |
|
RFI #: 29 | QUESTION: 'Can you please provide top/bottom of pile cap elevations? | ANSWER: Please see the response to RFI #11 |
|
RFI #: 30 | QUESTION: 'Confirming PC-1 and PC-2 piles are MP-1s (40k C / 24k T)? | ANSWER: Confirmed. |
|
RFI #: 31 | QUESTION: 'The use of duplex drilling with a down the hole hammer is prohibited? a. If so, is an adequate water supply accessible to each curve? b. With this number of piles, and the nature of the site. This could potentially mean we’d have to set up frac tanks, pumps, recycling system for the water. c. This is very hard rock, so utilizing just a roller bit will be very slow and difficult. | ANSWER: Please see the response to RFI #3 |
|
RFI #: 32 | QUESTION: 'Is there any opportunity to tap into a water line in the vicinity of the drilling/curves for the supply of water for drilling purposes? If not, what is the closest available water source? | ANSWER: See Section 01 51 21, sub-section 1.04-A. Water may be available at existing spigots/hydrants along the track until affected by work. If/when the existing track water line is affected, water will still be available on at the venue. |
|
RFI #: 33 | QUESTION: 'Since the existing access road is paved, and the contract language states that "The Contractor shall repair, construct, maintain access roads to various work zones..." it is highly probable that drilling equipment will damage a significant portion of this roadway. Is it your intention for the Contractor to include any and all asphalt repairs required in this Lump Sum contract price? | ANSWER: Refer to section 01 51 21 - Construction Facilities & Temporary Controls, sub sections 1.08-A and 1.08-B. Any and all repairs shall be perfromed at the contractors expense. |
|
RFI #: 34 | QUESTION: In Addendum #2, the revised plan sheet cover page has a revision cloud around the index of drawings, which lists sheet "C101 Overall Site Logistics Plan". This sheet is not included in the revised plan set. Please provide an up to date version of this sheet. | ANSWER: Consider exisiting Drawing C101 - Overall Site Logistics Pla, dated 12/13/24 as an up to date version. |
|
RFI #: 35 | QUESTION: 'Can you provide how the piles will be measured for payment? | ANSWER: Piles will be measure from pile tip to cutoff. |
|
RFI #: 36 | QUESTION: 'Please clarify the taxable status of this project and advise as to how the applicable taxes (if any) should be handled relative to the bid. | ANSWER: ORDA is a New York State Government Entity, thus it is exempt from taxes. A letter stating such can be provided upon request. |
|
RFI #: 37 | QUESTION: 'Please define the operational parameters needed to be observed to allow drilling to happen during track operations. | ANSWER: The Reference Project Schedule - Bid Milestone Schedule provided in Addendum #2 takes into account track operations. |
Below is a list of RFI questions submitted, along with accompanying answers for Contract Number: MVH.24.006.110 |
|||
RFI #: | QUESTION: | ADDENDUM #: | ANSWER: |
RFI #: 1 | QUESTION: Can you please confirm if the in person pre bid is mandatory if we are attending online? | ADDENDUM #: 1 | ANSWER: In-person pre-bid meeting is not mandatory. |
RFI #: 2 | QUESTION: Could you provide the meeting details for the pre bid scheduled tomorrow (12/4) at 1:30PM? | ADDENDUM #: 1 | ANSWER: The prebid meeting for MVH.24.006.110 MVH Sliding Track Modernization - Refrigeration Plant Replacement will be held both in-person and online. The in-person meeting will be at the mountain pass lodge at Mount Van Hoevenberg at the address below and the online meeting will be held on teams at the link below. Mountain Pass Lodge at Mt Van Hoevenberg 31 Van Hoevenberg Way Lake Placid, NY 12946 Microsoft Teams Need help? Join the meeting now Meeting ID: 236 904 030 511 Passcode: nw6gn6jD |
RFI #: 3 | QUESTION: Would the Owner kindly consider extending the bid date given the upcoming holidays and associated issues with obtaining pricing from subs/ suppliers during this time. Additionally, the information provided in the header of this web page indicates that the contract docs would be made available by 11/22 however the release date was 11/29. All things considered, we believe it would be in the best interest of all to push the bid date and allow the best possible pricing to be delivered to the Owner from prospective bidders. Please advise. | ADDENDUM #: 1 | ANSWER: The bid date will not be extended |
RFI #: 4 | QUESTION: Is there anyway the bid date could be extended to the first week of January? | ADDENDUM #: 1 | ANSWER: The bid date will not be extended. |
RFI #: 5 | QUESTION: Information provided during the prebid meeting indicated that there are currently no alternates for this project nor are there any anticipated. However, Section 01 23 00 includes (A.) Add Alternate No. 1- Snow Melt System. Please clarify. | ADDENDUM #: 1 | ANSWER: This will be addressed via addendum. |
RFI #: 6 | QUESTION: Is there a copy of the meeting that can be reviewed or some type of PowerPoint presentation? | ADDENDUM #: 1 | ANSWER: The Power Point presentation that was presented at the pre-bid meeting will be included in the first addendum. |
RFI #: 7 | QUESTION: Section 013573 “Delegated Design Procedures” requires that the refrigeration system design be performed under direct supervision of a PE experienced in design of this type of work. Will this be provided through White Mountain Engineering? Or are we to provide our own PE to stamp the delegated design documents? The safety relief system also required a stamp from a PE. Can this design be reviewed, approved & stamped through White Mountain Engineering? | ADDENDUM #: 1 | ANSWER: The Delegated Designer/Refrigeration Contractor can use any State of NY licensed PE with adequate and appropriate ammonia refrigeration design experience. |
RFI #: 8 | QUESTION: Per spec section 007213, paragraph 6.1.5 states the supervisory requirements on the project. Do these requirements solely pertain to the prime contractor, or are there similar requirements for any subcontractors, based on the dollar value of their individual contract? | ADDENDUM #: 1 | ANSWER: The requirement in section 00 72 13 solely pretain to the prime contractor. |
RFI #: 9 | QUESTION: The refrigeration system P&ID shows the compressor oil cooling as thermosyphon style, but the specifications call for liquid injection oil cooling. Is there a preference? How shall we quote this portion? | ADDENDUM #: 1 | ANSWER: Liquid Injection preferred due to elevation of existing condensers. |
RFI #: 10 | QUESTION: The refrigeration system P&ID shows an “plate evaporator” for the HVAC system, but there are no specifications to go with this unit. Will this heat exchanger be provided by others? Or will an addendum specify the requirements for this unit? | ADDENDUM #: 1 | ANSWER: No HVAC plate heat exchanger is to be provided. Space conditioning provided by standalone HVAC systems (by HVAC contractor) |
RFI #: 11 | QUESTION: Drawing C121 shows the refrigerant piping for the track labeled “Fuel”. The note states to “removed to extents necessary for connection to the new plant”. Will there be any more details regarding this exact tie-in location? Also, who will be responsible for isolating, pumping out and demo of the existing piping? Where are the closest isolation valves for these sections of piping and are there any access valves to assist with removing all ammonia liquid / vapor? | ADDENDUM #: 1 | ANSWER: For the purposes of this bid, assume the new refrigeration piping to extend 5'-0" outside the building, all track and exterior piping will be completed under a separate contract, MVH.24.006.190. |
RFI #: 12 | QUESTION: Who will be responsible for removing the existing 160,000lb ammonia charge? Will this need to be done before the track piping modifications are conducted? | ADDENDUM #: 1 | ANSWER: The removal of the existing charge will be performed under a separate contract. |
RFI #: 13 | QUESTION: Besides the tie-in sections of ammonia piping feeding the 3 track zones, are there any plans for demo of the existing system components & equipment to be included under this contract? | ADDENDUM #: 1 | ANSWER: The removal of the existing equipment will be performed under a separate contract. |
RFI #: 14 | QUESTION: Have there been any considerations for added structural supports needed for the ammonia receiver or flash economizer vessels? Drawing I101 shows the aisle locations for egress throughout the engine room, leaving very little floor space for any floor mounted vessels. | ADDENDUM #: 1 | ANSWER: Vessels will be small and floor mounted, locations of equipment shown are placeholders and subject to change during the final design. |
RFI #: 15 | QUESTION: With work being conducted on the track piping (by others) who will be responsible for pressure testing and leak checking the track piping? Will this new piping be dehydrated and/ or cleaned to avoid any water or debris from getting back to the new system? | ADDENDUM #: 1 | ANSWER: This scope will be performed under separate contract. Assume all new track piping with be clean and pressure tested. |
RFI #: 16 | QUESTION: The existing condensers will need to be re-piped to the new system. Are we to provide new refrigeration valves for the HSD, CD or purger lines at the unit? Or will we just be responsible for tying in the new piping after the existing isolation valves? | ADDENDUM #: 1 | ANSWER: New piping and valves required to comply with PID. |
RFI #: 17 | QUESTION: We request that the bid date be postponed from Tuesday 12/19, to Friday 1/17/25. The project was published on 11/22, which leaves a period of only three and a half weeks to complete the bid process, which was further compromised by the Thanksgiving Holiday. This project also contains a critical delegated design component, with the ammonia refrigeration system. This is a niche scope of work with limited qualified providers within the northeast. We’ve reviewed the project timeline with multiple of these firms, and several cannot commit to completing the required work to produce a design and cost estimate within this time frame. We are very interested in pursuing this project, but with the limited time available, we will not be able to turn in a bid. If the project can be postponed until after the holidays, we feel confident that it will increase the number of bids that ORDA receives and increase their competitiveness, resulting an overall lower cost. I understand that the project has a strict construction schedule to meet the objectives outlined in the project information, to have everything operational for the winter of 25/26. However, there are avenues to recoup time during the construction process through alternative work schedules and proper planning, which will allow the original schedule to be maintained. | ADDENDUM #: 1 | ANSWER: The Bid date will not be extended. |
RFI #: 18 | QUESTION: I cannot find any sheet metal or sheet metal flashing & trim specs. Please provide | ADDENDUM #: 1 | ANSWER: Specification will be included in Addendum 2 |
RFI #: 19 | QUESTION: No Roof Specs for the EPDM Roof System on the Main Roof Area DwgA311 | ADDENDUM #: 1 | ANSWER: Specification will be included in Addendum 2 |
RFI #: 20 | QUESTION: No Roof Specs for the TPO Roof System at the Curved Entry Canopy | ADDENDUM #: 1 | ANSWER: Specification will be included in Addendum 2 |
RFI #: 21 | QUESTION: Roof Assembly 01 shown on Dwg. A311 is calling for 2-Layers of 60Mil EPDM. Not familiar with this, can you provide additional details or information? | ADDENDUM #: 1 | ANSWER: Detail will be updated to show a single layer of 60 mil EPDM |
RFI #: 22 | QUESTION: Roof Assembly 01 indicates ¾” Structural Sheathing, please provide additional detail regarding this product. | ADDENDUM #: 1 | ANSWER: This is a non-structural sheething intended to be a barrier board. |
RFI #: 23 | QUESTION: Can you please have the architect review specification 074213.19 Insulated Metal Wall Panels. There are a lot of discrepancies in the specification compared to what is drawn. (Drawings show a 2.5” thick IMP, Spec lists 5” thick). | ADDENDUM #: 1 | ANSWER: The thickness of the IMP is based on the code min R-Value for exterior walls of R20.5 total so that will vary based on manufacturer. |
RFI #: 24 | QUESTION: No product or manufacturer is listed for the IMP. Please provide a list of acceptable products, or indicate if the “Kingspan-KS series” would be acceptable. (see attached data sheet). | ADDENDUM #: 1 | ANSWER: Kingspan-KS series is an acceptable product. |
RFI #: 25 | QUESTION: Is a 2 coat or 3 coat finished required? | ADDENDUM #: 1 | ANSWER: Assuming this is in regards to paint, typical installation is 1 coat primer and 2 coats of paint. |
RFI #: 26 | QUESTION: What gauge metal is required for the IMP? Will 22 gauge exterior with 26 gauge interior suffice? | ADDENDUM #: 1 | ANSWER: 22 gauge exterior with 26 gauge interior will suffice for IMP |
RFI #: 27 | QUESTION: Section: 241005: Page 1 of 7- Appears to be missing from the project manual. | ADDENDUM #: 1 | ANSWER: Section 24 10 04 Page 1 is on page 882 of the project manual. |
RFI #: 28 | QUESTION: After reviewing the project documents and the post bid documentation for the three low bidders. With the holiday we really would like to request a bid date extension in order to provide all post bid documentation if needed within the (2) days post bid. | ADDENDUM #: 1 | ANSWER: Due dates for post-bid submissions will not be extended. |
RFI #: 29 | QUESTION: The refrigeration P&ID shows (4) air cooled condensers sections. Meanwhile, the existing condensers to be reused only have (2) sections with discharge/drain/purge connections. Please clarify that the P&ID diagram is inaccurate on this matter. | ADDENDUM #: 1 | ANSWER: The PID is inaccurate, there are two existing air cooled condensors. |
RFI #: 30 | QUESTION: Specification 240015-2.5 specifies a gauge panel for pressure monitoring of the different system pressures, but this gauge panel is not shown on the drawings. Please provide confirmation that this is required. | ADDENDUM #: 1 | ANSWER: Provide guage panel. |
RFI #: 31 | QUESTION: The EPCS (Emergency Pressure Control System) is called out in the specifications, but not shown on the refrigeration P&ID. Though this safety is required per IIAR-2, could you please confirm this is required? | ADDENDUM #: 1 | ANSWER: EPCS is erquired to meet IIAR2. |
RFI #: 32 | QUESTION: The refrigeration P&ID shows 3 wet suction lines coming back from the three track zones. There is currently only one 12” suction line serving the three track zones. Who is responsible for running the new suction lines to the track and where are these to be tied in? Will additional piping supports need to be constructed? | ADDENDUM #: 1 | ANSWER: The sensors located outside of the new building will be provided under a separate contract. It is expected that any new controls on the track will be provided with dedicated control panels with ethernet communication back to the central system in the new building. |
RFI #: 33 | QUESTION: Has an Asbestos Survey been conducted on the garage that is to be demoed? | ADDENDUM #: 1 | ANSWER: Yes, but the garage demolition is not in the scope of work included in this bid. |
RFI #: 34 | QUESTION: With regard to the coiling door on the door schedule, the spec speaks about a fire door however the door schedule does not show any fire rating time. Is this a fire door? | ADDENDUM #: 1 | ANSWER: The overhead coiling door is not a fire door. |
RFI #: 35 | QUESTION: Please clarify the type of actuator required for the ammonia system pneumatic butterfly valves. Please include model numbers if available. | ADDENDUM #: 1 | ANSWER: Updated P&ID, as well as valve data sheets are included in Addendum #2. |
RFI #: 36 | QUESTION: Who is providing the VFDs for the ammonia liquid pumps. If we are to provide these, are there any associated specs? | ADDENDUM #: 1 | ANSWER: VFD's will be specificed and procured under electrical scope. Specificaiton will be included in Addendum #2. |
RFI #: 37 | QUESTION: Who is providing the VFDs for the refrigeration mechanical room exhaust fans. If we are to provide these, are there any associated specs? | ADDENDUM #: 1 | ANSWER: VFD's will be specificed and procured under electrical scope. Specificaiton will be included in Addendum #2. |
RFI #: 38 | QUESTION: Should questions be uploaded to this ORDA website or sent to the email provided in the documents, [email protected]? | ADDENDUM #: 2 | ANSWER: Questions should be uploaded to the ORDA website. |
RFI #: 39 | QUESTION: Reference 00 21 13, Instructions to Bidders. Section 4.2 Preparation of Bid states, "Bids shall be submitted in duplicate". Please confirm one original and one copy is acceptable. | ADDENDUM #: 2 | ANSWER: The duplicate copy of the bid submission does not need to be an original, only one original is required. |
RFI #: 40 | QUESTION: 00 11 14 Notice to Bidders states bids will be publicly opened and read at the Olympic Authority Administration Building located at 37 Church Street, Lake Placid, NY 12946, in the Conference Room located on the First Floor. Please confirm this is also the location for bid submission. | ADDENDUM #: 2 | ANSWER: The location in the Notice to Bidders is correct. |
RFI #: 41 | QUESTION: Given this bid is due close to the holidays (Thursday, December 19) Please clarify which post bid day deliverables may be requested of the 3 low bidders and the dates these deliverables are due. | ADDENDUM #: 2 | ANSWER: The date for documents due two (2) days after bids are due shall be 12/23/2024. |
RFI #: 42 | QUESTION: Drawing A211 Details 1 & 4 call for 5' clearance between bathroom vanity and wall for ADA compliance; additionally, the vanity is shown as a full cabinet resting on the floor. Drawing I100 calls for 4' clear dimension with a floating wall-mount vanity. Please clarify the dimension and type of vanity, and if this is to be an owner item or included in the bid. | ADDENDUM #: 2 | ANSWER: Per A101 and A211, 30" wide vanity is specified and should be included in project. |
RFI #: 43 | QUESTION: Reference A102 & I101. No finish plan is provided for the mezzanine. Please advise if this area is to receive paint, base, flooring, etc. or if it is to be left unfinished. | ADDENDUM #: 2 | ANSWER: Mezanine finish is plywood from floor/ceiling assembly and sheetrocked walls with primer. |
RFI #: 44 | QUESTION: Reference C131. The plant list calls for 10 balsam fir trees (type AB) but the drawing shows 5 trees. Please confirm the correct quantity of balsam fir trees. | ADDENDUM #: 2 | ANSWER: 10 type AB Balsam Fir should be provided per plant list. Five (5) unidenfified trees on plan are intended to be AB Balsam Fir. |
RFI #: 45 | QUESTION: NYS is establishing a Contractor Registration requirement. Starting December 30, 2024, all contractors and subcontractors submitting bids or performing construction work on public work projects or private projects covered by Article 8 of the Labor Law are required to register with the New York State Department of Labor (NYSDOL) under Labor Law Section 220-i. Please clarify, is the Contractor required to have completed the registration process at the time of bid submission or at the time of project commencement? Are subcontractors required to have completed the registration process at the time of bid submission or at the time of project commencement? | ADDENDUM #: 2 | ANSWER: The Contractor and subcontractors will be required to register with the New York State Department of Labor under Labor Law Section 220- i prior to the commencement of work on the Project. |
RFI #: 46 | QUESTION: Per Article 25 of the General Specifications. Paragraph 25.4 states that all structural steel, reinforcing steel and other major steel items be made in the USA. Please advise if this applies to the steel piping to be used for the refrigeration system. There does not seem to be any mention of this requirement in spec section 242010 – Ammonia Piping. | ADDENDUM #: 2 | ANSWER: Section 25.4 of the Contract Document 00 72 13 General Conditions does not apply to the steel piping to be used for the refrigeration system. |
RFI #: 47 | QUESTION: A601. Door schedule indicates (3) doors with closet function hardware. Are these to be keyed alike to the entry doors, or separately? If separately, are they to be keyed alike to each other? | ADDENDUM #: 2 | ANSWER: All locksets shall be 7 pin SFIC with construction cores. The construction cores will be removed at handover and cores will be installed by the venue. |
RFI #: 48 | QUESTION: Are the (3) Stairs to be metal pan or grated tread | ADDENDUM #: 2 | ANSWER: Grated tread. |
RFI #: 49 | QUESTION: What kind of railings are to be on the stairs? Standard Picket rail? | ADDENDUM #: 2 | ANSWER: Railings must meet building code requirements for height and clear openings. |
RFI #: 50 | QUESTION: Is interior steel to be painted or unpainted? Specs and drawings are unclear. | ADDENDUM #: 2 | ANSWER: Interior steel shall be shop primed and painted at all exposed steel per note 6, sheet S110. |
RFI #: 51 | QUESTION: Specification section 133419 Metal Building Systems. Please provide clarity between this spec section and the structural steel, steel joist and metal decking specified in division 5. This project doesn't appear to be a "typical" metal building project. the grating over the gantry area is to be galvanized or painted. | ADDENDUM #: 2 | ANSWER: 133419 Metal Building Systems has been removed from the set. Grating over lower level pump pit shall be galvanized. |
RFI #: 52 | QUESTION: Do you plan on waiving the below specification on this project? 1.6 QUALITY ASSURANCE A. Fabricator Qualifications: A qualified fabricator that participates in the AISC Quality Certification Program and is designated an AISC-Certified Plant, Category BU or is accredited by the IAS Fabricator Inspection Program for Structural Steel (Acceptance Criteria 172) | ADDENDUM #: 2 | ANSWER: No, AISC certification is required from the fabricator on this project. |
RFI #: 53 | QUESTION: Reference A111 & A112. Per the Reflected Ceiling Plans for Level 1 and Level 2 it shows an exposed roof structure. However, it does not show if the exposed roof structure should be painted or not. Please confirm if the exposed roof structure needs to be painted. | ADDENDUM #: 2 | ANSWER: Painting not required on exposed roof steel. |
RFI #: 54 | QUESTION: Reference Detail 1/A311. Per the drawings and details it indicates the integral bases are 6" or 8". Can you confirm which base we should be quoting. | ADDENDUM #: 2 | ANSWER: 8” epoxy cove base. |
RFI #: 55 | QUESTION: A111 'First Floor Reflected Ceiling Plan', Room 106 shows a 1 hour rated ceiling system per UL assembly G556. However, UL assembly G556 is a 2-hour assembly with floor structure as part of the system. There is no floor system shown at this location. Please confirm if we should price a UL assembly G556 for the ceiling in room 106. | ADDENDUM #: 2 | ANSWER: Ceiling for room 106 must be 1-Hr UL rated ceiling – there is no floor assembly above – disregard G556 designation. |
RFI #: 56 | QUESTION: A111 ' First Floor Reflected Ceiling Plan' Room 107 states there is an optional No Ceiling in Janitors closet. However, it shows a gypsum board ceiling as well. Please confirm how we should price this ceiling. | ADDENDUM #: 2 | ANSWER: Bid should not include a ceiling. |
RFI #: 57 | QUESTION: Metal stud blocking at roof coping - Please confirm how the exposed edge of the metal stud blocking gets finished. | ADDENDUM #: 2 | ANSWER: Wrap with fascia material; typ. |
RFI #: 58 | QUESTION: Reference A202. What is the base material for the veneer stone entry posts? Final selection by owner, is there a spec? | ADDENDUM #: 2 | ANSWER: Stone shall be black bear ganite with ashlar coursing pattern to match the remainder of the campus and new construction. |
RFI #: 59 | QUESTION: Reference 00 42 01.01 - Project Labor Agreement List of Subcontractors. Please confirm that the only subcontractors to be named on this form are providing work in a minimum of one (1) of the three (3) listed categories: Plumbing & Gas Fitting; Steam Heating, Hot Water Heating, Ventilating and AC Apparatus; or Electric Wiring and Standard Illuminating Fixtures. | ADDENDUM #: 2 | ANSWER: Section 00 21 13 - "Instructions to Bidders" Part 4.8 discusses requirements for the List of Subcontractors. |
RFI #: 60 | QUESTION: Reference 00 21 12 - Encouraging Use of New York State Businesses in Contract Performance. Form indicates that if NY businesses are to be used in the performance of the contract, bidder is to "identify New York State businesses that will be used and attach identifying information." Please confirm additional subcontractor information, beyond subcontractors listed on the Project Labor Agreement List of Subcontractors, is due post bid. | ADDENDUM #: 2 | ANSWER: This can be submitted post-bid. |
RFI #: 61 | QUESTION: Please reference 00 21 00 - Bid Form - Project Labor Agreement, page 3. Item 4 provides a checklist of bid day deliverables. Please clarify, is the List of Similar Projects (Document 00 45 15) mislabeled? 00 45 15 does not exist. Should this reference, List of Completed Similar Construction Project (00 21 03)? | ADDENDUM #: 2 | ANSWER: List of similar drawings is mislabeled on the bid form. The correct document is List of Completed Similar Construction Project (00 21 03) |
RFI #: 62 | QUESTION: Specs 062023 and 064023 are provided for interior arch. woodwork and finish carpentry, however neither appear to be present on the drawings. Please confirm if these spec sections are relevant to the project, and if so, where? | ADDENDUM #: 2 | ANSWER: These specification are for vanity, kitchenette, & locker cubbies as shown on interior elevation sheets. |
RFI #: 63 | QUESTION: Drawings A311 (detail 3) and A601 call for opening 109 to be an overhead coiling door, however, specs (083613) have also been provided for sectional doors. Additionally, Spec 083323 describes mechanical and power-operated functions for this door, but no power is provided per drawing E101. Please confirm 1.) that the door is to be an overhead coiling door and Spec 083613 is obsolete; and 2.) whether the door is to be power-operated or mechanical function. | ADDENDUM #: 2 | ANSWER: Overhead coiling door will be power-operated. |
RFI #: 64 | QUESTION: Drawing A601 calls for all doors to be HM and all windows to be steel frame. Specs have been provided for aluminum storefronts (084113) and aluminum windows (085113). Please confirm 1.) that all windows are to be HM borrowed lites with glazing per the window schedule; and 2.) that spec sections 084113 & 085113 are obsolete. | ADDENDUM #: 2 | ANSWER: 1.) Confirmed, 2.) Confirmed |
RFI #: 65 | QUESTION: NYS is establishing a Contractor Registration requirement. Starting December 30, 2024, all contractors and subcontractors submitting bids or performing construction work on public work projects or private projects covered by Article 8 of the Labor Law are required to register with the New York State Department of Labor (NYSDOL) under Labor Law Section 220-i. Please clarify, if a subcontractor listed on 00 42 01.01 Project Labor Agreement List of Subcontractors is unable to obtain the NYS DOL registration, is the contractor permitted to select another subcontractor without incurring any penalties? | ADDENDUM #: 2 | ANSWER: The Contractor and subcontractors will be required to register with the New York State Department of Labor under Labor Law Section 220- i prior to the commencement of work on the Project. |
RFI #: 66 | QUESTION: Per spec section 240010-2.1.7 The owners ammonia compliance consultant shall provide SOPs with input from the refrigeration contractor. Who is the owners ammonia compliance consultant? Can their contact info please be provided? | ADDENDUM #: 2 | ANSWER: Heather Young - Ammonia Safety Management, Inc |
RFI #: 67 | QUESTION: There is no mention as to who is responsible for furnishing & installing the Motor Control Center for the smaller starters & drives for the condensers, exhaust fans, Etc. Please confirm who will be responsible for procuring this. Labeled as “SB” on DWG E101. | ADDENDUM #: 2 | ANSWER: “SB” is the main switchgear that was an early procurement, owner furnished and contractor installed item. There is no motor control center. The design call for distribution panels that feed VFDs that feed pumps. The contractor is responsbile for wiring these to the BMS/ammonia control system which will turn them on and off as required for system operation. |
RFI #: 68 | QUESTION: Per MB RFI #10 regarding the condenser piping & valve replacements. The isolation valves are to be replaced at the unit, therefore, a pumpout of the refrigerant in the condenser coils is required. Who will be responsible for removing this ammonia? | ADDENDUM #: 2 | ANSWER: The facility/owner will pump down the system after the event season has ended, by April 1, 2025 |
RFI #: 69 | QUESTION: There appears to be a mistake on S121 where the Roof Deck Schedule was copied instead of Elevated Slab Schedule. Please provide correct schedule. | ADDENDUM #: 2 | ANSWER: The roof deck is applicable to the partial roof plan on 2/S121. The mezzanine floor is ¾” plywood deck per 1/S121. |
RFI #: 70 | QUESTION: Response to questions posted on the ORDA website references Addendum 01 and Addendum 02. Please provide addenda. | ADDENDUM #: 2 | ANSWER: Addendum 01 was released on 12/11/2024 and Addendum 02 are forthcoming. |
RFI #: 71 | QUESTION: Reference Drawing C161 - New Refrigeration Supply lines. This drawing indicates to see structural drawings for the support footing for the new refrigerant lines but the structural drawings don’t show them. Please provide a detail for the new refrigeration line supports. | ADDENDUM #: 2 | ANSWER: Concract only includes piping to 5' outside building envelop. Elevated pipe and pipe supports will be executed under contract MVH.24.006.190. |
RFI #: 72 | QUESTION: The insurance requirements indicate the GL Additional Insured endorsement shall be the CG 20 10 11 85 edition. Please confirm, is the CG 20 10 12 19 edition acceptable? | ADDENDUM #: 2 | ANSWER: Either endorsement will be acceptable. |
RFI #: 73 | QUESTION: Spec 101423.16 details room identification signage but nothing is shown in the drawings. Is this spec relevant to the project and if so, is there signage to be located on every door or just specific rooms? | ADDENDUM #: 2 | ANSWER: Signage to be provided on all interior doors, style and lables to be coordinated with Owner. |
RFI #: 74 | QUESTION: Various bathroom specialties are noted on drawing I100, with only the soap dispensers noted as owner furnished contractor installed. No spec section is provided for any bathroom specialties. Please confirm if these are to be included in the bid, owner furnish contractor installed, or excluded from the bid. | ADDENDUM #: 2 | ANSWER: GC to furnish & install all bathroom accessories shown and detailed on drawings. |
RFI #: 75 | QUESTION: A101 calls for all cabinets/casework by owner. Specifications are provided for plastic laminate clad countertops (123623.13). Please clarify what to price regarding furnish and install of cabinets and countertops. | ADDENDUM #: 2 | ANSWER: Counter tops and cabinets to be furnushed & installed by GC. Follow spec sections for laminate clad countertops. Cabinetry to be laminate clad plywood cabinetry. |
RFI #: 76 | QUESTION: Drawing M601; ELECTRIC UNIT HEATER SCHEDULE shows unit heaters to be rated as explosion proof. The electrical drawings do not designate any electrically hazardous locations. Please indicate the extent and classification of the classified hazardous areas within the building for pricing the electrical work properly. | ADDENDUM #: 2 | ANSWER: There is no explosion proof requirements in the pump room. |
RFI #: 77 | QUESTION: Neither of the acceptable refrigeration compressor manufacturers supply ABB drives as a standard option. Therefore, the level of manufacturer support is limited and could lead to drive communication problems. Please advise if a comparable substitution will be acceptable for these drives. | ADDENDUM #: 2 | ANSWER: Per equipment schedule on E601, "VFD must be Square D Altivar 680 AFE Low Harmonic Process Drive" |
RFI #: 78 | QUESTION: the pit area, the only information we find is 1 ½”x1/8” and no further description. | ADDENDUM #: 2 | ANSWER: 19-space 1 ½” x 1/8” galvanized bar grating with manufacturer standard attachments |
RFI #: 79 | QUESTION: There is a spec provided for 06 18 00 Glued-Laminated Construction within the project manual, however the PLA and MWBE outreach presentation state this material is a separate bid package as a furnish only contract for early procurement. Please confirm this material has already been purchased and clarify the intent is for the refrigeration plant contractor to install only. Confirm the following specs are not applicable to refrigeration plant work. 064023 Interior Architectural Millwork 081216 Aluminum Frames 083613 Sectional Doors 084113 Aluminum Framed Entrances and Storefronts 123623 Plastic Laminated Clad Countertops 133419 Metal Building Systems | ADDENDUM #: 2 | ANSWER: Materials that will be supposed to the contractor are included in Appendix "L" |